HAZARD MITIGATION PLAN TOWN OF RINDGE, NH · 2014. 1. 24. · HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (2024)

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (1)

2007

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH

Courtesy of the Rindge Historical Society

Prepared by the:

Town of Rindge Hazard Mitigation Committee

&

Southwest Region Planning Commission 20 Central Square, 2nd Floor

Keene, NH 03431 (603) 357-0557 www.swrpc.org

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (2)

Rindge Hazard Mitigation Plan- 2007

ii

TABLE OF CONTENTS EXECUTIVE SUMMARY.................................................................................................................. vi

I. INTRODUCTION ............................................................................................................................... 1

Background...................................................................................................................................... 1 Authority.......................................................................................................................................... 1 Funding Source................................................................................................................................ 1 Purpose ............................................................................................................................................ 1 Scope of the Plan ............................................................................................................................. 2 Methodology.................................................................................................................................... 2 Acknowledgements.......................................................................................................................... 4 Hazard Mitigation Goals of Rindge, NH......................................................................................... 5 Resource List for Hazard Mitigation Committee............................................................................. 6

II. COMMUNITY PROFILE ................................................................................................................... 7

Town Overview ............................................................................................................................... 7 Disaster Risk.................................................................................................................................... 8 Development Patterns...................................................................................................................... 9 Consideration for Development..................................................................................................... 10 Current Development Trends ........................................................................................................ 11 Road Improvement ........................................................................................................................ 11 Development in Hazard Areas....................................................................................................... 12 National Flood Insurance Program (NFIP).................................................................................... 12

III. HAZARD IDENTIFICATION............................................................................................................ 13

Hazards .......................................................................................................................................... 13 Past and Potential Hazards............................................................................................................. 14

Flooding- Disaster Declarations.............................................................................................. 14 Riverine Flooding – Low Risk ................................................................................................ 14 Flooding – Medium Risk......................................................................................................... 15 Drought – Low Risk................................................................................................................ 15 Extreme Heat – Low Risk ....................................................................................................... 16 Wildfire – Medium Risk ......................................................................................................... 16 Lightning Strikes – Medium-High Risk.................................................................................. 16 Tornado – Low-Medium Risk................................................................................................. 17 Hurricane – Low-Medium Risk .............................................................................................. 17 Earthquake – Low-Medium Risk ............................................................................................ 18 Severe Wind/Downburst – Low-Medium Risk....................................................................... 19 Extreme Winter Weather – Low-Medium Risk ...................................................................... 19 Man-Made Hazards / Hazardous Materials – Low-Medium Risk .......................................... 20 Snow Avalanche – Low Risk .................................................................................................. 20 Subsidence – Low Risk ........................................................................................................... 20 Radon Air/Water – Low Risk.................................................................................................. 20 Man-Made Hazards / Dams – Medium Risk........................................................................... 21

Past and Potential Hazards Map ....................................................................................Back of Plan IV. ASSESSING PROBABILITY, SEVERITY AND RISK, ESTIMATING POTENTIAL LOSSES ............... 23

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (3)

Rindge Hazard Mitigation Plan- 2007

iii

V. CRITICAL FACILITIES....................................................................................................................24

Category 1 – Emergency Response Services................................................................................. 24 Emergency Operations Center ................................................................................................ 24 Fire Station .............................................................................................................................. 24 Police Station .......................................................................................................................... 24 Emergency Fuel Facilities....................................................................................................... 24 Emergency Electrical Power Facility ...................................................................................... 24 Emergency Shelters................................................................................................................. 24 Dry Hydrants – Fire Ponds – Water Sources .......................................................................... 24 Primary Evacuation Routes..................................................................................................... 25 Bridges Located On Primary Evacuation Routes.................................................................... 25 Town Garage/Transfer Station ................................................................................................ 25 Communications ..................................................................................................................... 25 Hospitals.................................................................................................................................. 25

Helicopter Landing Sites ......................................................................................................... 25 Category 2 – Non-Emergency Response Facilities ....................................................................... 25

Water Supply........................................................................................................................... 25 Sewer Infrastructure ................................................................................................................ 25 Problem Culverts..................................................................................................................... 25 Transfer Station....................................................................................................................... 25 Secondary Evacuation Route .................................................................................................. 26 Bridges on Secondary Evacuation Routes............................................................................... 26

Category 3 – Facilities/Populations to Protect............................................................................... 26 Special Needs Population........................................................................................................ 26 Recreation Areas ..................................................................................................................... 26 Schools .................................................................................................................................... 26 Day Care Facilities .................................................................................................................. 26 Churches.................................................................................................................................. 26 Historic Buildings/Sites .......................................................................................................... 27 Camps/Parks/Campgrounds .................................................................................................... 27 Inns.......................................................................................................................................... 27 Employment Centers ............................................................................................................... 27 Apartment Complexes............................................................................................................. 27 Post Office............................................................................................................................... 27 Hazardous Material Storage .................................................................................................... 27

Category 4 – Potential Resources .................................................................................................. 27 Food ........................................................................................................................................ 27 Water ....................................................................................................................................... 28 Hospitals/Medical Supplies..................................................................................................... 28 Gas .......................................................................................................................................... 28 Heating Fuel ............................................................................................................................ 28 Building Material and Heavy Equipment Supplies................................................................. 28 Miscellaneous Resources ........................................................................................................ 28

Critical Facilities and Evacuation Routes Potentially Affected by Hazard Areas………………..29

Critical Facilities Map ...................................................................................................Back of Plan

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (4)

Rindge Hazard Mitigation Plan- 2007

iv

VI EXISTING MITIGATION STRATEGIES AND PROPOSED IMPROVEMENTS....................................30

School Evacuation Plan........................................................................................................... 30 Town Adopted Building Code ................................................................................................ 30 Code Enforcement Officer ...................................................................................................... 30 Emergency Management Plan................................................................................................. 30 Health Officer.......................................................................................................................... 30 Fire Inspector .......................................................................................................................... 30 Emergency Back-Up Power Program ..................................................................................... 30 Local Road Design Standards ................................................................................................. 30 Local Bridge Maintenance Program ....................................................................................... 30 Local Road Maintenance Program.......................................................................................... 31 Tree Maintenance Program ..................................................................................................... 31 Winter Storms Operations Plan............................................................................................... 31 Town Master Plan ................................................................................................................... 31 Steep Slopes Protection........................................................................................................... 31 Mutual Aid .............................................................................................................................. 32 Other Mutual Aid .................................................................................................................... 32 Fire Dry Hydrant Management Plan ....................................................................................... 32 Spill Prevention Control and Counter Measures Plan............................................................. 32 Town Warning System............................................................................................................ 32 Erosion and Sedimentation Plan ............................................................................................. 32 Wetlands Protection ................................................................................................................ 32 Town Radio System ................................................................................................................ 33 Shoreland Protection Act ........................................................................................................ 33 Town-Sponsored Safety Awareness Program......................................................................... 33 Ambulance Service ................................................................................................................. 33 Radiological Evacuation Plan ................................................................................................. 33

Preliminary Prioritization .............................................................................................................. 33 Recommended Improvements Ranking......................................................................................... 34

VII. MITIGATION STRATEGIES.............................................................................................................35

Preventative (Programs/Policies)................................................................................................... 35 Training ......................................................................................................................................... 35 Public Education & Information.................................................................................................... 35 Engineering.................................................................................................................................... 36 Property Protection ........................................................................................................................ 36 Structural Projects.......................................................................................................................... 36 Equipment Purchases..................................................................................................................... 36 Preliminary Prioritization .............................................................................................................. 36 Mitigation Strategies Ranking ....................................................................................................... 37 Potential Hazards Location Mitigation Actions............................................................................. 38 Preliminary Prioritization .............................................................................................................. 38 Potential Hazard Actions Matrix ................................................................................................... 39 Potential Hazard Actions Ranking................................................................................................. 41

VIII. PRIORITIZED IMPLEMENTATION SCHEDULE AND ACTION PLAN…………..............….……...42

Summary of Critical Evaluation .................................................................................................... 42 Implementation Schedule and Action Plan.................................................................................... 42 Prioritized Implementation Schedule............................................................................................. 43

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (5)

Rindge Hazard Mitigation Plan- 2007

v

IX. ADOPTION, IMPLEMENTATION, MONITORING & UPDATE..........................................................46

Adoption ........................................................................................................................................ 46 Monitoring & Updates ................................................................................................................... 46 Implementation of the Plan through Existing Programs................................................................ 46

Certificate of Adoption ................................................................................................................... 48

APPENDICES Hazard Descriptions........................................................................................................Appendix A Resources........................................................................................................................Appendix B Hazard Mitigation Resources Profiles ............................................................................Appendix C Matrix of Federal All Hazard Grants ..............................................................................Appendix D Documentation of the Planning Process ......................................................................... Appendix E Public Relations .............................................................................................................. Appendix F Project Status Sheets .......................................................................................................Appendix G

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (6)

Rindge Hazard Mitigation Plan-2007

vi

Executive Summary

The Rindge Hazard Mitigation Plan serves as a means to reduce future losses from natural or man-made hazard events before they occur. The Plan was developed by the Rindge Hazard Mitigation Committee and contains statements of policy adopted by the Board of Selectmen. Natural hazards are addressed as follows: • Flooding (Riverine, Ice/Snow Melt) • Wind (Downburst, Tornado & Hurricane) • Wildfire • Extreme Winter Weather • Subsidence • Radon (Air/Water)

• Drought • Extreme Heat • Earthquakes • Lightning • Man-Made (Hazardous Materials/Dam Breach)

The Rindge Hazard Mitigation Committee, as shown per Chapters III and IV, identified “Critical Facilities” and “Areas at Risk” as follows: Critical Facilities • Emergency Operations Center • Fire Station • Police Station • Emergency Fuel Facilities • Emergency Electrical Power

Facility • Emergency Shelters • Dry Hydrants/Fire Ponds/Water

Sources • Evacuation Routes & Bridges

(Primary & Secondary) • Town Garage / Transfer Station • Communications • Hospitals • Helicopter Landing Sites

Areas at Risk • Old New Ipswich Road • Conservation Lands • Construction site on US 202

North • Fuel stations throughout town • US 202 North at Jaffrey T/L • Franklin Pierce University

Road • Intersection of US 202/NH 119

The Rindge Hazard Mitigation Committee identified existing hazard mitigation programs as follows: • Emergency Management Plan • School Evacuation Plan • Fire Dry Hydrant Management

Plan • Town Warning System • Local Road Design Standards • Local Bridge Maintenance

Program • Local Road Maintenance

Program • Tree Maintenance Program • Code Enforcement Officer • Fire Inspector • Health Officer • Building Codes • Shoreland Protection Program • Winter Storms Operations Plan

• Hazardous Materials Spill Prevention Control & Counter Measures Plan

• Town Radio System • Mutual Aid • Erosion and Sedimentation

Plan • Emergency Power Back-up

Program • Town Master Plan • Wetlands Protection Ordinance • Safety Awareness Program • Ambulance Service • Radiological Evacuation Plan • Steep Slopes Ordinance

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (7)

Rindge Hazard Mitigation Plan-2007

vii

The Rindge Hazard Mitigation Committee prioritized newly identified hazard mitigation strategies as follows: 1. Sandbag program (stockpile materials & organize volunteers) 2. Portable generators for sump pumps and to power up homes of special needs populations 3. Portable Pumps 4. Detours – Acquire cones, barriers, and signs and educate public on detour routes 5. Buy additional radio frequencies and 2 repeaters (radio interoperability) 6. Beaver control program 7. Conduct survey of residents regarding vulnerability and volunteer opportunities 8. ATV’s (Rhinos) & Boats for rescue 9. Install more dry hydrants 10. Coordinate Yankee evacuation plans with the State 11. Power back up for signals at the intersection of routes 119/202 12. Acquire CB & HAM radio for Emergency Operations Center 13. Expand existing surface water testing 14. Reverse 911 system 15. RMS School power backup 16. Franklin Pierce Shelter power back up 17. Power back up for Town Hall 18. Fuel spill containment booms, training, and inspection of gas stations 19. Fix Culvert on Old New Ipswich Road 20. Resolve Mutual Aid radio jams during VT Yankee drills 21. Emergency Transportation Plan for moving people to shelters 22. Neighborhood level plans, with town coordinator designated to each 23. Coordination of volunteers and private resources (snowmobiles, ATVs, etc.) 24. Securing supplies with retail stores 25. Coordinate School Superintendent w/ FD & PD re: days off & trouble students 26. Radiological training for monitors 27. Public education on town warning signals and procedures for extended power outages 28. New fire codes for commercial buildings (more stringent sprinkler regulations) 29. Dam inspection policy 30. Implement septic system ordinance 31. Acquire excavator for Public Works 32. Forest Management practices for conservation lands to prevent forest fires 33. Code enforcement –environmental training for health officer 34. Erosion Sediment Control ordinance 35. Snow fencing/landscaping to prevent white-outs on College Road 36. Security fence around explosives storage area 37. Public sewer around lakes (such as little Michigan)

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (8)

Rindge Hazard Mitigation Plan- 2007

1

CHAPTER I INTRODUCTION

Background The Federal Emergency Management Agency (FEMA) has mandated that all communities within the State of New Hampshire establish local hazard mitigation plans as a means to reduce future losses from natural or man-made hazard events before they occur. In response to this mandate, the NH Bureau of Emergency Management (BEM) contracted the Southwest Region Planning Commission (SWRPC) to develop a program that would achieve this goal. SWRPC prepared a hazard mitigation planning handbook to be used by local communities as a guide in the preparation of hazard mitigation plans. SWRPC then facilitated two hazard mitigation planning processes with selected communities as pilot projects. The resulting plans laid the foundation in an effort to enable all New Hampshire Regional Planning Commissions, through education outreach, the capability to assist their local communities, such as the Town of Rindge, in the preparation of local hazard mitigation plans.

What is Hazard Mitigation?

Authority

This Hazard Mitigation Plan was prepared under the authority of the Planning Mandate of Section 409 of Public Law 93-288 as amended by Public Law 100-707, the Robert T. Stafford Act of 1988, hereinafter referred to as the "Stafford Act." Accordingly, this All-Hazard Mitigation Plan will be referred to as the "Plan."

Funding Source This Plan was funded by the NH Bureau of Emergency Management, with grants from the Predisaster Mitigation Competitive Grant Program as well as from funds appropriated by the Town of Rindge.

Purpose The Rindge All-Hazard Mitigation Plan is a planning tool to be used by the Town of Rindge, as well as other local, state and federal governments, in their efforts to reduce the effects from natural and human-made hazards. This plan does not constitute any sections of Rindge's Master Plan or Town Ordinances.

“Hazard Mitigation means any action taken to reduce or eliminate the long-term risk to human life and property from natural hazards” (44 CFR 206.401).

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (9)

Rindge Hazard Mitigation Plan- 2007

2

Scope of the Plan

The scope of this Plan includes the identification of natural hazards affecting the Town of Rindge, as identified by the Hazard Mitigation Committee. The hazards were reviewed under the following categories as outlined in the State of New Hampshire's Natural Hazards Mitigation Plan:

I. Flood, Erosion, Drought, Extreme Heat and Wildfire. II. Geological Hazards (Earthquake, Subsidence, and Radon). III. Severe Wind (Tornado, Hurricane, Thunderstorm, Downburst and Lightning). IV. Winter Weather (Snow, Ice Storm and Extreme Cold).

The Committee also discussed man-made hazards such as Dams and Hazardous Materials Spills.

Methodology

Using the Guide to Hazard Mitigation Planning for New Hampshire Communities handbook, the Rindge Hazard Mitigation Committee developed the content of the Rindge’s Hazard Mitigation Plan by following the nine step process set forth in the handbook. The Committee held monthly meetings, open to the public including area business owners, schools, organizations and communities, starting April 20, 2006 through November 2, 2006, in order to develop the Plan. On Enter Date the Rindge Board of Selectmen held a public hearing and adopted the Plan. The following are dates of Committee meetings and sub-committee meetings. Public Committee Meetings: April 20, 2006, 7:00 - 8:30 p.m.: Public informational and organizational meeting, held at Rindge Town Offices. May 22, 2006, 7:00 - 9:00 p.m.: Working committee meeting held at Rindge Town Offices. June 6, 2006, 10:00 - 12:00 p.m.: Working committee meeting held at Rindge Town Offices. July 11, 2006, 10:00 - 1:00 p.m.: Working committee meeting held in Rindge Town Offices. August 8, 2006, 10:00 - 1:00 p.m.: Working committee meeting held in Rindge Town Offices. September 19, 2006, 10:00 - 1:00 p.m.: Working committee meeting held in Rindge Town Offices. November 2, 2006, 10:30 – 12:00 p.m.: Working committee draft plan review meeting held at Rindge Town Offices. A mailing was made to each committee member, prior to each meeting that contained information from the previous meeting, an agenda sheet, and information to be covered. In addition, the meetings were advertised as a public meeting in accordance with RSA 91-A, and the meeting dates where posted on the town’s website. (Meeting agendas and notices are included in Appendix D at the back of the Plan.) Public Meetings with the Board of Selectmen: Insert Date: The Board of Selectmen agreed to begin the process of developing a Local Hazard Mitigation Plan. Meeting held at Rindge Town Offices. INSERT DATE.: The Board of Selectmen adopted the Local Hazard Mitigation Plan. Public hearing held at Rindge Town Offices.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (10)

Rindge Hazard Mitigation Plan- 2007

3

The Committee developed this Plan as a result of following the described meeting procedures and planning steps: Step 1: Establish and Orient a Hazard Mitigation Planning Committee Southwest Region Planning Commission presented the Town of Rindge with recommendations for the make up of the committee. Recommendations included the inclusion of town staff, emergency response staff, public works, elected officials, business owners, and those with knowledge of historical events. Town staff selected persons based on these recommendations and submitted a list of prospective members to the Board of Selectmen. The Selectmen approved the members and the committee was formed. Step 2: Identification of Hazards and Critical Facilities As listed below, the Committee members identified human-made and natural hazards that could or have affected the Town of Rindge. Flooding Tornado Hazardous Materials Spills Drought Hurricanes Snow Avalanche Extreme Heat Earthquakes Subsidence Wildfire Severe Wind/Downburst Radon Lightning Strikes Extreme Winter Weather Dams The Committee brainstormed on the type of hazards and locations that have sustained or could be susceptible to each hazard within the Town. The results are shown in the Past and Potential Hazard Map, which can be found at the end of the Plan. The Committee then identified and catalogued all of the critical facilities within the Town. The result is found in Chapter IV, "Critical Facilities Analysis," and shown on a location map at the end of the Plan. Step 3: Assessing Probability, Severity and Risk, and Estimating Potential Losses The Committee members completed Risk Assessment Worksheets for all of the types hazards identified in Step 2 in order to assess probability, severity and risk. Potential losses for each hazard type were estimated. This data is found in Chapter IV “Assessing Probability, Severity and Risk- Estimating Potential Losses.” Step 4: Analyze Development Trends This Step was conducted by town staff and the Regional Planning Commission. The results of this research were shared with the Committee and can be found in Chapter II, “Community Profile.” Step 5: Existing Mitigation Strategies and Proposed Improvements The Committee identified plans and policies that are already in place to reduce the affects of man-made and natural hazards. Then the Committee evaluated the effectiveness of the existing measures to identify where they can be improved. The results are found in Chapter VII, "Existing Mitigation Strategies." The Committee also identified programs in place that would not be categorized as mitigation strategies. Step 6: Brainstorm and Develop Disaster Minimization Alternatives To assist with determining mitigation projects, the Committee considered the following eight (8) objectives:

Preventative (Programs & Policies) Property Protection Structural Public Education & Information

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (11)

Rindge Hazard Mitigation Plan- 2007

4

Engineering Projects Equipment Purchase Training

The Committee also identified mitigation actions for each of the potential hazards identified in Chapter III. Step 7: Prioritized Mitigation Measures The Committee developed a prioritized list of mitigation projects identified in Step 6 considered feasible to implement. This prioritized list can be found in Chapter VII. Step 8: Develop an Implementation Strategy- Action Plan Using the prioritized list of mitigation actions identified in Step 7, the Committee developed a clear strategy that outlines who is responsible for implementing each project, as well as when and how the actions will be implemented. Step 9: Adopt and Implement the Plan The Committee members reviewed and approved each section of the plan as it was completed. After acceptance by the Committee, the Plan was submitted to the New Hampshire Bureau of Emergency Management for initial review, and then forwarded to FEMA, for formal approval. Once approved, the Plan was formally adopted by the Town of Rindge on _____________. The Committee approved the "Prioritized Mitigation Projects" list, which identifies responsibility, funding, support and timeframe for each project. Other projects that may be developed with the support of Rindge’s Emergency Management Director shall be led by the head of the department that shares that responsibility. The Town Administrator should be charged with requesting annual reports as to the progress of each project. It is important to the Town of Rindge that this plan be monitored and updated annually or after a presidentially declared disaster. Chapter VIII addresses this issue.

Acknowledgements

The Rindge Board of Selectmen extends special thanks to the Rindge Hazard Mitigation Committee as follows: Rickard Donovan, Director of Public Life and Safety Carlotta Pini, Assistant to the Town Administrator Patricia Barry, Selectmen Bob Cleland, Historical Society & Conservation Committee Jo Anne Carr, Town Planner Michael Sielicki, Police Chief Robert Forrest, Director Public Works Michael A. Cloutier, Sr., Highway Foreman Evelyn Fogg, Business Owner The Rindge Board of Selectmen offers thanks to the New Hampshire Bureau of Emergency Management for developing the State of New Hampshire Natural Hazards Mitigation Plan (www.nhoem.state.nh.us) which served as a model for this plan. In addition, special thanks are extended to the staff of the Southwest Region Planning Commission for professional services, process facilitation and preparation of this document.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (12)

Rindge Hazard Mitigation Plan- 2007

5

Hazard Mitigation Goals

Town of Rindge, NH

The overall Goals of the Town of Rindge with respect to Hazard Mitigation are stipulated here:

1. To improve upon the protection of the general population, the citizens of the Town of Rindge and guests, from all natural and human-made hazards.

2. To reduce the potential impact of natural and man-made disasters on the Town of Rindge's Emergency Response Services.

3. To reduce the potential impact of natural and human-made disasters on the Critical

Facilities in the Town of Rindge.

4. To reduce the potential impact of natural and human-made disasters on the Town of Rindge's infrastructure.

5. To improve the Town of Rindge's Emergency Preparedness and Disaster Response and Recovery Capability.

6. To reduce the potential impact of natural and human-made disasters on private property in the Town of Rindge.

7. To reduce the potential impact of natural and human-made disasters on the Town of Rindge's economy.

8. To reduce the potential impact of natural and human-made disasters on the Town of Rindge's natural environment.

9. To reduce the Town of Rindge's liability with respect to natural and human-made hazards through a community education program.

10. To reduce the potential impact of natural and human-made disasters on the Town of Rindge’s specific historic treasures.

11. To identify, introduce and implement cost-effective Hazard Mitigation measures so as to

accomplish the Town's Goals and Objectives and to raise the awareness of and acceptance of Hazard Mitigation opportunities generally.

12. The Town of Rindge will work in conjunction and cooperation with the State of New

Hampshire's Hazard Mitigation Goals.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (13)

Rindge Hazard Mitigation Plan- 2007

6

Resource List for Hazard Mitigation Committee

The following list are agencies whose advice was either actively sought in the creation of this plan, or with whom future contacts should be made in carrying out this plan.

New Hampshire Bureau of Emergency Management:

Division of Emergency Management 33 Hazen Drive, Concord, NH 03305

Field Representative: Jeremy LaPlante 603-223-3613 Mitigation Officer: Richard Verville 1-800-852-3792

New Hampshire Department of Transportation: James Mitchell (District 4) Swanzey, NH 03446 352-2302 Public Service of New Hampshire: Sue Blothenberg Keene, NH 03431 357-7309 Ext. 5115

1-800-662-7764 Cold Region Research Laboratory: Kate White Hanover, NH 03755 646-4187 Rindge Memorial School Principal: John Stone Rindge, NH 03461 899-3363

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (14)

Rindge Hazard Mitigation Plan- 2007

7

CHAPTER II COMMUNITY PROFILE

The Town of Rindge’s master plan and annual report were reviewed and compiled along with up-to-date information from various agencies of the State of New Hampshire and from the Southwest Region Planning Commission. This information, along with anecdotal and factual information from the Hazard Mitigation Committee was used to provide the following profile. Town Overview

The Town of Rindge is located in the southeastern portion of Cheshire County, in Southwest New Hampshire. Rindge is bounded on the north side by Jaffrey and Sharon, easterly by New Ipswich, westerly by Fitzwilliam, and southerly by the State of Massachusetts. The Town population is 6,137.1

Location Map of Rindge, NH

The Town of Rindge has a density of 165.6 persons per square mile of land area and contains 37.1 square miles of land area and 2.7 square miles of inland water area. The Town has several significant water bodies, such as Lake Monomonac, Contoocook Lake, Emerson Pond, Grassy Pond, Hubbard Pond, Bullet Pond, Pool Pond, Crowcroft Pond and Pearly Pond. Some of these water features have attracted a substantial amount of shoreline development which consists mostly of seasonal dwellings on small, nonconforming lots of records that were subdivided may years ago. More recently, year-round residences have been built. Additionally, Rindge has large amounts of undeveloped land: 3,831 developed acres and 20,069 undeveloped acres.2 1 Population data from Office of Energy & Planning’s 2004 Population Estimates 2 1989 data from the Town of Rindge Master Plan (2001 Update)

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (15)

Rindge Hazard Mitigation Plan- 2007

8

Rindge has two different watersheds. The Contoocook River watershed, which is part of the Merrimack River Basin, drains approximately 30% of the Town (7,450 acres) to the north. The Millers River watershed is part of the Connecticut River Basin and drains approximately 70% of Rindge (18,150 acres) to the south.

The topography of Rindge is more of a rolling terrain characterized by broader and more gradual slopes than the steeper slopes found in neighboring Jaffrey and New Ipswich. The overall change in topography ranges from a low of approximately 900 feet in the extreme southwest corner near the Fitzwilliam/Rindge/Massachusetts border to approximately 1,500 feet in the extreme southeast corner adjacent to the New Ipswich town line. High points in Rindge are Thrasher Hill 1,382’ and Griswold Hill 1,371’. However, the general terrain ranges mostly in the 1,000 – 1,200 foot elevation.

Rindge has a mid-latitude climate. Average summer temperature is 68 degrees Fahrenheit; average winter temperature is 20 degrees Fahrenheit. Average annual precipitation is 45 inches and the average annual snowfall is 74 inches. Two major highways pass through Rindge; NH Route 119 and US Route 202. Route 119 is the major east-west artery and Route 202 is the major north-south artery.

A three-member Board of Selectmen governs the Town of Rindge. The Town has a full-time Town Administrator, full-time Fire Chief (Director of Public and Life Safety) with a volunteer Fire Department, a full-time Police Chief, and a full-time Director of Public Works. Area hospitals include the Cheshire Medical Center/Dartmouth-Hitchcock located in Keene, approximately 22 miles northwest, Monadnock Community Hospital in Peterborough, approximately 14 miles north of Rindge, and Heywood Hospital in Gardner, MA, approximately 16 miles south. Disaster Risk

Rindge is prone to a variety of man-made and natural hazards. These include: vehicle accidents, dam failures, riverine and ice jam flooding, erosion, severe wind events, wildfire, drought, ice storms and severe winter storms. Rindge does not have the same flooding problems as communities to the north which border the Contoocook River because flooding is moderated by an extensive drainage network and the capacity of wetlands to store floodwaters. This allows the waters to be dispersed over a large area and discharged over a longer period of time.

Severe wind events and hurricane residuals have caused damage to Rindge. Over the years unrecorded wind events have caused losses of timber. In 1928, a tornado ripped through West Rindge causing major property damage. Wildfires have occurred in Rindge as well. There have been several documented wildfires throughout town in the past 70 years. The areas in and around the forests are susceptible to wildfires due to the fuel load and many camping activities. Winter weather has proven to be a regular hazard throughout the town of Rindge each year. Rindge is susceptible to receiving large volumes of snow from Nor’easters due to its geographical close proximity to the east coast where these storms track. In 1888, Rindge received 40 inches of snow from one of these storms. The town has also received a fair share of damage from ice storms in winter months.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (16)

Rindge Hazard Mitigation Plan- 2007

9

Development Patterns Examination of the Town’s existing land use as shown in the 1990 Rindge Master Plan indicates that most of the Town’s land area (about 78.4% land) is undeveloped and consists primarily of wooded and brush-covered areas, many of which have substantial development constraints. Rindge’s most prevalent natural limitation for development is its wetlands. Twenty-six percent of the Town’s area is undevelopable, approx. nineteen percent is comprised of wetland soils and another approx. seven percent is surface water.

EXISTING LAND USE IN RINDGE, 1980 AND 1989*

% OF % OF TOTAL ACRES ACRES IN USE TOTAL LAND LAND USE 1980 1989 1980 1989 1980 1989 DEVELOPED:

Resident ia l ( s ingle & mul t i ) 930 2103 34 .7 55 .0 3 .7 8 .2 Commercia l 130 97 4 .8 2 .5 0 .5 0 .4 Indust r ia l 10 21 0 .3 0 .5 0 .0 0 .1 Publ ic / Ins t i tu t iona l 990 950 36 .9 24 .8 3 .9 3 .7

Roads and Highways 625 660 23 .3 17 .2 2 .4 2 .6 TOTALS 2 ,685 3 ,831 100% 100% 10 .5% 15 .0% UNDEVELOPED 21,215 20,069 82 .9% 78.4% Water Area 1 ,700 6 .6% 6 .6% TOTAL AREA 25 ,600 100 .0% 100.0% * Decrease in commerc ia l and publ ic / ins t i tu t iona l acreage i s due to d i f fe rences in c lass i f ica t ion methods . Source: Rindge Comprehensive Plan, 1980 and Southwest Region Planning commission, 1988, Rindge Master Plan, p2-11.

Residential Land devoted to residential uses comprises the largest amount of developed acreage in Rindge. Reference to the Existing Land Use Map reveals that the pattern of residential development generally follows the natural features of the land and the existing road network. Today’s residential pattern consists mainly of single family detached dwellings located on various town roads as well as routes 202 and 119. Agriculture/Vacant Land Analysis of the present development pattern reveals that agricultural activity has experienced a significant decline in Rindge even though, according to the 1980 Master Plan, the Town once contained some of the most productive farms in the State. Evidence of agricultural activity consisted mainly of hay fields and pastures, and there are only a few active farms still in existence. Numerous vacant areas that were obviously farm fields are currently lying fallow and/or have become overgrown with brush and show evidence of returning to forest land. Commercial The greatest concentrations of commercial development are to be found on the southern section of US 202, which is Rindge’s main commercial area. Most of Rindge’s commercial activity is located in this area.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (17)

Rindge Hazard Mitigation Plan- 2007

10

Industrial There are two areas of industrial uses in town, located in the northwest area along US 202 near the Jaffrey town line and along US 202 south near the Massachusetts state line. There are also a few sand and gravel pits operating in Town. Recreational There are many recreational uses in Town. They include the school properties, town and private beaches, Franklin Pierce sports complex, the many private campgrounds and picnic areas, the lakes, and other attractions. Forest Land Heavily wooded forest land still covers most of the Town. Most of this land has already been cut for lumber in previous years (dating back to the early 1800s), and so there are no “virgin” stands of timber remaining. Forested land often includes the steeper slopes and wetlands that heretofore have remained undeveloped. These wooded areas still produce timber. They are also important to the town’s landscape because they serve as a recreational resource, provide wildlife habitat, help moderate the climate, and help maintain the rural character of the town. Roads and Highways Roads and highways comprise a major portion of a community’s developed land area. In Rindge, the land devoted to the Town and State roads occupies approximately 660 acres or 17.2% of the total developed area (92.92 miles). The land consists of both the traveled road surface and the adjacent right-of-way area. Public/Institutional Development Numerous public and private institutional uses are located in Rindge. The 1980 plan showed institutional acreage to be approximately 990 acres. Public facilities include cemeteries, The Old Meeting House, Town Office Building, Rindge Elementary School, Fire Station, Town Forest, Post Office, Wellington Road Recreation Area, State Highway Barn, Annett State Forest, Town Garage, and Solid Waste Transfer Station. Private Facilities include Churches, Franklin Pierce University, Camp Quinapoxet Boy Scout Camp, Camp Monomonac, Hampshire Country School, Cathedral of the Pines Memorial, Meeting School, and Camp Joy. Rindge is still basically a rural community with three small village centers. The villages of Rindge Center and West Rindge have a fairly concentrated development pattern consisting primarily of residential uses supplemented by commercial (along Route 202) and various public and semi-public uses. The village of East Rindge is strictly a residential neighborhood.

Consideration for Development The existing topography of Rindge will play a significant role in the location of future land uses such as residential, commercial, and industrial. Rindge contains a significant amount of wetlands and some steep slopes that are not really suitable for development. As a result, development will be oriented to those portions of the Town where such physical constraints will not present significant development problems. Also, developers can use the planned residential development or cluster development concept to mitigate adverse environmental considerations. It is also expected that future development will be oriented to the larger undeveloped land parcels that are scattered throughout the Town.

Analysis of the Natural Features Maps shows that many of these areas are located in close proximity to Routes 119 and 202 and would be easily accessible from these highways. Consequently, it is expected that much of the Town’s future growth will be attracted to, and located in, these highway corridors. It is

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (18)

Rindge Hazard Mitigation Plan- 2007

11

expected that the present topography, when coupled with existing soil conditions, will be a major determinant as to where future development will or will not occur in Rindge.

The soils best suited for development in Rindge are the Monadnock, Colton, and Berkshire soils. Most of these soils are on 8-15% slopes and would need erosion and sedimentation control plans when development is proposed on these soils. There is a high permeability rate in the Colton soils and groundwater quality should be a concern for development.

Many of the other soil units in Rindge are rated medium to high for development potential, but many of these soils pose severe restrictions for septic systems due to a restrictive hardpan layer.

Current Development Trends Overall, land use patterns in Rindge are dominated by single family residential development, with fairly significant retail development along US 202. Within Rindge there are also seasonal lakefront properties as well as a large college (Franklin Pierce University). This general pattern is not expected to change, although the Planning Department is very concerned about increased residential development occurring in the eastern part of town (east of US 202). Agriculture, which continues to be a concern, both for the economic activity as well as for the protection of the prime farmlands, does not play a significant role in the local economy. It is unlikely that this will change in the foreseeable future, due as much to national trends in farming as to anything else.

Significant features of the built environment include the Town Center on Payson Hill Rd., the retail development on US 202, and the Franklin Pierce University campus. Rindge's history and traditions are rich, and much attention - both public and private - is given to preserving these features. With the pending increase in development, this is a good time to review the land use regulations relative to protecting the identity and character of the Town; this includes addressing land use along the roads.

The future of the NH 119 and US 202 retail corridors and Franklin Pierce University will have tremendous impact on the whole town. Attention will need to be paid to the land use regulations to ensure that they support the final goals and plans for these important pieces of property.

Based on data collected and analyzed in the Land Use Analysis chapter of Rindge’s Master Plan (2001), certain assumptions can be made in anticipating future development in Rindge.

• If the past 10 years can serve as an indicator, Rindge will continue to see significant increase in population, new homes built, and retail development.

• The road network in and through Rindge will remain unchanged over the next 10-15 years, aside from regular maintenance and improvements. The roads carrying traffic through Rindge, i.e., Routes 119 and 202, will continue to serve as subregional arterials and local collectors.

• Subdivisions will continue to occur in the eastern side of town with mainly single family homes being built on them.

Road Improvements Providing an adequate thoroughfare and transportation system is the most significant public investment activity in the physical development of a town. The existing transportation network, which in the case of Rindge refers exclusively to the system of roads and highways, has a profound influence on the location and development of various land uses through the Town. Due to the significant financial commitment required for the improvement and maintenance of the road network, and the direct relationship between land use patterns and traffic circulation with the Town, the

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (19)

Rindge Hazard Mitigation Plan- 2007

12

identification and analysis of current transportation needs is crucial to the orderly accommodation of growth and development. Development in Hazard Areas Some hazards identified in this plan are regional risks and, as such, all new development falls into a hazard area. The exception to this is flooding. Currently, there are no structures located within the Special Flood Hazard Area (SFHA) in Rindge. According to the Community Information System (CIS) of FEMA, there have been no development permits and no variances granted within the SFHA since 1978, the earliest records kept in the CIS for the Town of Rindge. There are currently 13 flood insurance policies in force for a total value of $1,598,700, with no claims since 1978. National Flood Insurance Program (NFIP) Areas susceptible to flooding present obvious hazards to life and property, and the continued protection of these areas from development is an important responsibility. Rindge participates in the National Flood Insurance Program administered by the Federal Emergency Management Agency (FEMA). FEMA conducted a flood hazard study for Rindge in 1997 and flood hazard areas were identified in the Pool Pond and Contoocook Lake areas, as well as areas along the Millers River and Lake Monomonac. Flood Insurance Rate Map (FIRM) and Flood Hazard Boundary Maps were prepared by FEMA and are available for review at the Rindge Planning Board office.3

3 Rindge Master Plan – 2006, Natural Resources Chapter, p. 3-17, 8.3 Floodplains

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (20)

Rindge Hazard Mitigation Plan- 2007

13

CHAPTER III: HAZARD IDENTIFICATION

The following is a list of natural and manmade disasters, and the areas affected by them, that have or could affect the Town of Rindge. These hazards were identified from the State of New Hampshire Hazard Mitigation Plan (2004), the Federal Emergency Management Administration website, and in a brainstorming session with the Hazard Mitigation Planning Committee meeting on May 22, 2006. The Past and Potential Hazards Map at the end of this Plan reflects the contents of this list.

Hazards

Riverine Flooding Flooding- Disaster Declarations

Flooding- Localized areas Drought

Extreme Heat Wildfires Lightning Tornadoes Hurricanes

Earthquakes Severe Wind/Downbursts Extreme Winter Weather

Hazardous Materials Incidents Snow Avalanche

Subsidence Radon Dams

In order to determine estimated losses due to natural and man made hazards in Rindge, each hazard area was analyzed; results are shown below. Human losses were not calculated during this exercise, but could be expected to occur depending on the type and severity of the hazard. Most of these figures exclude both the land value and contents of the structure. The value of all structures, including exempt structures such as schools and churches, is $ 552,374,838.00, as of December 1, 2005.4 The median value of a home in Rindge is $114,400 according to the 2000 Census. 5 The data below was calculated using FEMA’s Understanding Your Risks: Identifying Hazards and Estimating Losses (August 2001). In addition, the Committee completed the Vulnerability Assessment Worksheets which provided more data to estimate the potential losses. As future development in Rindge is unpredictable at this time, it is uncertain as to how many future structures could be threatened by hazards. Only existing structures are considered. 4 NH Department of Revenue Administration 5 Median home value from 2000 Census may not fully reflect current median home values. In the event of a hazard incident, a current home value data should be used to estimate losses.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (21)

Rindge Hazard Mitigation Plan- 2007

14

Hazard Date Location Severity

Remarks/Description of Areas Impacted

FLOODING- DISASTER DECLARATIONS

Flood 1927 Southern NH Damage to Road Network. Caused many roads to wash out.

Flood March 11-21, 1936 NH State

Damage to Road Network. Flooding caused by simultaneous heavy snowfall totals, heavy rains and warm weather. Run-off from melting snow with rain overflowed the rivers

Flood/ Severe Storm August 27, 1986 Cheshire, Hillsborough

Counties, NH FEMA Disaster # 771-DR (Presidentially Declared Disaster) $1,005,000 in damage

Flood / Severe Storm April 16, 1987

Cheshire, Carroll, Grafton, Hillsborough,

Merrimack, Rockingham, & Sullivan Counties, NH

FEMA Disaster Declaration # 789- DR (Presidentially Declared Disaster). Flooding of low-lying areas along river caused by snowmelt and intense rain. $4,888,889 in damage.

Flood August 7-11, 1990

Belknap, Carroll, Cheshire, Coos, Grafton, Hillsborough, Merrimack & Sullivan Counties, NH

FEMA Disaster Declaration # 876. Flooding caused by a series of storm events with moderate to heavy rains. $2,297,777 in damage.

Storms/ Flood January 3, 1996 Carroll, Cheshire, Coos,

Grafton, Merrimack, Sullivan Counties, NH

FEMA Disaster Declaration # 1077-DR. Damage amount $2,220,384.

Flood July 2, 1998 Southern NH FEMA Disaster Declaration # 1231. Severe storms and flooding

Heavy Rain/ Flood

September 18-19, 1999

Belknap, Cheshire, Grafton Counties, NH

FEMA Disaster Declaration # DR-1305-NH. Heavy rains associated with Tropical Storm/Hurricane Floyd.

Severe Storm/ Flood September 12, 2003 Cheshire and Sullivan

Counties, NH FEMA Disaster Declaration # 1489-DR. Damage amount $1,300,000.

Flood October 26th 2005

Cheshire, Grafton, Merrimack, Sullivan, and Hillsborough Counties,

NH

FEMA Disaster Declaration # 1610. Severe storms and flooding.

RIVERINE FLOODING- LOW RISK

Riverine Flooding

Past and Potential Occurrences

Contoocoock Lake & Poole Pond

Flooding of the lake and intermittent streams onto US 202 has occurred and has the potential to occur annually in this area due to accumulation of heavy rain, runoff, and construction of beaver dams. This section of US 202 is located in the 100-year floodplain. Although past flooding has occurred along the road, there is no record of damage.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (22)

Rindge Hazard Mitigation Plan- 2007

15

Hazard Date Location Severity

Remarks/Description of Areas Impacted

FLOODING- LOCALIZED- MEDIUM RISK

Flood Past and Potential Occurrences

Northern Hubbard Pond (map #15)

Floods over road due to heavy rain and spring thaw. Town is at peak of watershed, few flooding events.

Flood Past and Potential Occurrences

Old New Ipswich Road (map #14)

Beaver Dams cause flooding during heavy rain events due to heavy overflow.

Flood Past Occurrences Lake Monomanoc Dam (map #21) This dam has been recently repaired.

Flood Past and Potential Occurrences

Mill Pond and Island Pond (map #20)

Hampshire County School owns dam. The state was helping in the repair of the dam when it failed in the summer of 2006. No damage was reported due to the failure.

Flood Potential Occurrence Annette Dam (map #19)

Annette dam has been repaired in the last 10 years. It would cause major flooding in Jaffrey if it failed.

Flood Potential Occurrence Grassy Pond Road (map #18)

Major event could cause flooding to houses in this location.

Flood Potential Occurrences

Old Cathedral Road (map #17)

Stream has potential for flooding one house. Beaver dam is causing potential flooding.

DROUGHT- LOW RISK Drought 1929-1936 Statewide Regional. Recurrence Interval 10 to > 25 years

Drought 1939-1944 Statewide Severe in southeast and moderate elsewhere. Recurrence Interval 10 to > 25 years

Drought 1947-1950 Statewide Moderate. Recurrence Interval 10 to > 25 years

Drought 1960-1969 Statewide

Regional longest recorded continuous spell of less than normal precipitation. Encompassed most of the Northeastern US. Recurrence Interval > 25 years

Drought 2001-2002 Statewide

Third worst drought on record, exceeded only be the drought of 1956-1966 and 1941-1942.

Rindge has had limited experience with severe drought conditions. Drought will increase the risk of wildfire, especially in areas of high recreational use and forested areas. Forested areas with high fuel content have more

potential to burn

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (23)

Rindge Hazard Mitigation Plan- 2007

16

Hazard Date Location Severity

Remarks/Description of Areas Impacted

EXTREME HEAT- LOW RISK

Extreme Heat July, 1911 New England 11-day heat wave in New Hampshire

Extreme Heat Late June to September, 1936 North America Temps to mid 90s in the northeast

Extreme Heat Late July, 1999 Northeast 13+ days of 90+ degree heat

Extreme Heat Early August, 2001 New Hampshire Mid 90s and high humidity

Extreme Heat August 2-4, 2006 New Hampshire Regional heat wave and severe storms, New Ipswich provided a cooling center at the Ambulance Bay

Elderly are at risk; however, potential risk is low. Approximately 7.7% of the town population is 65 and over. Quantity of and access to water sources throughout town reduces potential risk

WILDFIRES- MEDIUM RISK

Wildfire Past Occurrence Eastern Shore of Lake Monomonac

A bottle rocket ignited brush and burned down a cabin and many trees

Wildfire 1926 Village center Burned down in 1926.

As forested areas are protected through preservation and conservation, debris builds up on the ground, increasing the fuel load and potential wildfire. Entire town - minimal forest fire protection (dependent on

on-call firefighters and problems with accessibility). . All forested areas – have high potential for fire, with 6” to 10” of brush creating high fuel load. Peat moss creates possibility of underground fires. Lightning

strike areas also prone to wildfires. LIGHTNING- MEDIUM- HIGH RISK

Lightning Past and Potential Occurrences

Pearly Lake

Lightning strikes at private residences on Pearly Lake.

Lightning Past and Potential Occurrences

US 202 south

Lightning has struck several times at businesses along US 202

Lightning Past and Potential Occurrences

Old New Ipswich Rd

Lightning strikes have been reported on the northern portion of this road. Two power lines and many trees destroyed.

Lightning Past and Potential Occurrences

Bancroft Reservoir Lightning strikes reported in this area.

Lightning Past and Potential Occurrences

High Tension power lines

Lightning has struck in the vicinity of the high tension power lines going from Main St. to Goddard Rd

Rindge has experienced several lightning strikes to private properties. High elevations and areas around lakes and wetlands may be more susceptible to lightning strike incidents.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (24)

Rindge Hazard Mitigation Plan- 2007

17

Hazard Date Location Severity

Remarks/Description of Areas Impacted

TORNADOS (1950-2003, Fujita Scale given if known)- LOW-MEDIUM RISK Tornado September 15, 1922 Cheshire County F2

Tornado September 13, 1928 Cheshire County

F2- tornado incident followed the approximate route from Franklin Pierce road to Payson Hill Road along NH 119. The tornado caused an estimated $100,000 (1928 dollars= $1,066,424 in 2005) mostly in property damage

Tornado August 13, 1963 Cheshire County F2 Tornado June 6, 1963 Cheshire County F2 Tornado July 2, 1997 Cheshire County F1

Tornadoes rarely occur in this part of the country; therefore, assessing damages is difficult. Buildings have not been built to Zone 2, Design Wind Speed Codes. Estimated damages to 10% of structures with 20% damage is

$11,047,4986. Estimated cost does not include building contents, land values or damages to utilities. River corridors and hill tops susceptible. 13 incidents of tornadic activity (F1 or less) occurred in Cheshire County

between 1959 - 1991 HURRICANES (Category given if known) and TROPICAL STORMS- LOW-MEDIUM RISK

Hurricane August, 1635 n/a Hurricane October 18-19, 1778 n/a Winds 40-75 mph Hurricane October 9, 1804 n/a

Gale September 23, 1815 n/a Winds > 50mph Hurricane September 8, 1869 n/a

Hurricane September 21, 1938 Southern New England

Flooding caused damage to road network and structures. 13 deaths, 494 injured throughout NH. Disruption of electric and telephone services for weeks. 2 Billion feet of marketable lumber blown down. Total storm losses of $12,337,643 (1938 dollars). 186 mph maximum winds.

Hurricane (Carol) August 31, 1954 Southern New England Category 3, winds 111-130 mph. Extensive tree

and crop damage in NH, localized flooding

Hurricane (Edna) September 11, 1954 Southern New England

Category 3 in Massachusetts. This Hurricane moved off shore but still cost 21 lives and $40.5 million in damages throughout New England. Following so close to Carol it made recovery difficult for some areas. Heavy rain in New Hampshire

Hurricane (Donna) September 12, 1960 Southern and Central NH Category 3 (Category 1 in NH). Heavy flooding

in some parts of the State.

Tropical Storm (Daisy) October 7, 1962 Coastal NH Heavy swell and flooding along the coast

Tropical Storm (Doria) August 28, 1971 New Hampshire Center passed over NH resulting in heavy rain

and damaging winds Hurricane

(Belle) August 10, 1976 Southern New England Primarily rain with resulting flooding in New Hampshire. Category 1

6 2005 Tax Valuations, from http://www.nh.gov/revenue/property_tax/2005/2005 tax rate reports.xls

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (25)

Rindge Hazard Mitigation Plan- 2007

18

Hazard Date Location Severity

Remarks/Description of Areas Impacted

Hurricane (Gloria) September, 1985 Southern New England

Category 2, winds 96-110 mph. Electric structures damaged; tree damages. This Hurricane fell apart upon striking Long Island with heavy rains, localized flooding, and minor wind damage in New Hampshire

Hurricane (Bob) August 19, 1991 Southern New England

Structural and electrical damage in region from fallen trees. 3 persons were killed and $2.5 million in damages were suffered along coastal New Hampshire. Federal Disaster FEMA-917-DR

Hurricane (Edouard) September 1, 1996 Southern New England

Winds in NH up to 38 mph and 1 inch of rain along the coast. Roads and electrical lines damaged

Tropical Storm (Floyd)

September 16-18, 1999 Southern New England FEMA DR-1305-NH. Heavy Rains

Tropical Storm (Tammy) October 5-13, 2005 East Coast of US

Remnants of Tammy contributed to the October 2005 floods which dropped 20 inches of rain in some places in NH.

Rindge’s location in southwestern New Hampshire reduces the risk of extremely high winds that are associated with hurricanes. The Town has experienced small blocks of downed timber and uprooting of trees onto

structures. Hurricanes can and do create flooding. Estimated wind damage 5% of the structures with 10% damage is $2,761,874. Estimated flood damage 10% of the structures with 20% damage is $11,047,498. Cost

of repairing or replacing the roads, bridges, utilities, and contents of structures is not included EARTHQUAKES (Magnitude given if known)- LOW-MEDIUM RISK

Earthquake 1638 Central New Hampshire 6.5-7

Earthquake October 29, 1727 Off NH/MA coast Widespread damage Massachusetts to Maine

Earthquake December 29, 1727 Off NH/MA coast Widespread damage Massachusetts to Maine

Earthquake November 18, 1755 Cape Ann, MA 6.0, much damage

Earthquake 1800s Statewide NH 83 felt earthquakes in New Hampshire

Earthquake 1900s Statewide NH 200 felt earthquakes in New Hampshire

Earthquake March 18, 1926 Manchester, NH Felt in Hillsborough County

Earthquake December 20, 1940 Ossipee, NH

Earthquake December 24, 1940 Ossipee, NH

Both earthquakes of magnitude 5.5, both felt for 400,000 sq miles, structural damage to homes, damage in Boston MA, water main rupture.

Earthquake December 28, 1947 Dover-Foxcroft, ME 4.5

Earthquake June 10, 1951 Kingston, RI 4.6

Earthquake April 26, 1957 Portland, ME 4.7

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (26)

Rindge Hazard Mitigation Plan- 2007

19

Hazard Date Location Severity

Remarks/Description of Areas Impacted

Earthquake April 10, 1962 Middlebury, VT 4.2

Earthquake June 15, 1973 Near NH/Quebec Border, NH 4.8

Earthquake January 19, 1982 Gaza (west of Laconia), NH

4.5, walls and chimneys cracked, damage up to 15 miles away in Concord

Earthquake October 20, 1988 Near Berlin, NH 4 Moderate potential for serious damage in older portions of town and around lakes. Structures are mostly of

wood frame construction estimated loss 20% of town assessed structural valuation (or $110,474,968). Costs of repairing or replacing roads, bridges, power lines, telephone lines, or the contents of the structures are not

included. Town should consider seismic design in building code SEVERE WIND/DOWNBURST- LOW-MEDIUM RISK

Town at risk - severe localized blasting winds. Structural damage potential. Such events cause small blocks of downed timber. Frequent occurrences in spring and fall. EXTREME WINTER WEATHER- LOW-MEDIUM RISK

Snow Storm 1888 New Hampshire 40 inches fell in the Rindge area

Ice Storm December 17-20, 1929 New Hampshire

Unprecedented disruption and damage to telephone, telegraph and power system. Comparable to 1998 Ice Storm (see below)

Blizzard February 14-17, 1958 New Hampshire 20-30 inches of snow in parts of New Hampshire

Snow Storm March 18-21, 1958 New Hampshire Up to 22 inches of snow in south central NH

Snow Storm December 10-13, 1960 New Hampshire Up to 17 inches of snow in southern NH

Snow Storm January 18-20, 1961 New Hampshire Up to 25 inches of snow in southern NH

Snow Storm February 2-5, 1961 New Hampshire Up to 18 inches of snow in southern NH

Snow Storm January 11-16, 1964 New Hampshire Up to 12 inches of snow in southern NH

Blizzard January 29-31, 1966 New Hampshire 3rd and most severe storm of 3 that occurred over a 10-day period. Up to 10 inches of snow across central NH

Snow Storm December 26-28, 1969 New Hampshire Up to 41 inches of snow in west central NH

Snow Storm February 18-20, 1972 New Hampshire Up to 19 inches of snow in southern NH

Snow Storm January 19-21, 1978 New Hampshire Up to 16 inches of snow in southern NH

Blizzard February 5-7, 1978 New Hampshire New England-wide. Up to 25 in of snow in central NH

Snow Storm February, 1979 New Hampshire President's Day storm Ice Storm January 8-25, 1979 New Hampshire Major disruptions to power and transportation

Snow Storm April 5-7, 1982 New Hampshire Up to 18 inches of snow in southern NH

Ice Storm February 14, 1986 New Hampshire

Fiercest ice storm in 30 yrs in the higher elevations in the Monadnock region. It covered a swath about 10 miles wide from the MA border to New London NH

Extreme Cold Nov- Dec, 1988 New Hampshire Temperature was below 0 degrees F for a month

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (27)

Rindge Hazard Mitigation Plan- 2007

20

Hazard Date Location Severity

Remarks/Description of Areas Impacted

Ice Storm March 3-6, 1991 New Hampshire Numerous outages from ice-laden power lines in southern NH

Ice Storm January 15, 1998 New Hampshire

Federal disaster declaration DR-1199-NH, 20 major road closures, 67,586 without electricity, 2,310 without phone service, $17+ million in damages to Public Service of NH alone. The incident affected the entire town except for a portion in the southern part. No damage to structures was caused by the incident. See Appendix G for affected areas map.

Snow Storm March/April 2001 New Hampshire Several multiple-feet snow events. Three types of winter events are heavy snow, ice storms and extreme cold. Occasionally heavy snow will collapse buildings. Ice storms have disrupted power and communication services. Timberland has been

severely damaged. Extreme cold affects the elderly. Rindge's recent history has not recorded any loss of life due to the extreme winter weather. These random events are difficult to set a cost to repair or replace any of the

structures or utilities affected. Elderly are affected by extreme weather. HAZARDOUS MATERIALS SPILLS- LOW-MEDIUM RISK

Public transportation of chemicals and bio-hazardous materials through town on NH 119 is a concern. Hazardous materials are also stored at the fireworks store and storage facility on US 202 north. There are three

gas stations on NH 119, as well as a marina on the southern point of Lake Monomonac SNOW AVALANCHE- LOW RISK

If a snow avalanche were to occur, it could cause damage to roads, bridges, utilities, houses, and other structures. The town does not have steep slopes capable of causing avalanches. The Town has no history of snow avalanche events. If information becomes available regarding vulnerable risk locations or avalanche

occurrences, the plan will amended accordingly SUBSIDENCE- LOW RISK

Subsidence Past and Potential Occurrences

US 202

Subsidence has occurred and has potential to occur in an area along US 202 on the Jaffrey Town Line. The road in this area is slowly settling, and it does not seem like a rapid and catastrophic failure could happen

Predictable areas susceptible to subsidence could be along old river channels, quarries or old land fills. RADON- LOW RISK

Summary Table of Short-term Indoor Radon Test Results in NH’s Radon Database (5/7/99) County # Tests G. Mean Maximum % > 4.0 pCi/l % > 12.0 pCi/l Belknap 744 1.3 22.3 14.4 1.3 Carroll 1042 3.5 478.9 45.4 18

CHESHIRE 964 1.3 131.2 15.6 2.3 Coos 1072 3.2 261.5 41 17

Grafton 1286 2.0 174.3 23.2 5.2 Hillsborough 2741 2.1 202.3 29.6 6.8 Merrimack 1961 2.0 152.8 25.2 6

Rockingham 3909 3.0 155.3 40 9.5 Strafford 1645 3.4 122.8 44 13 Sullivan 466 1.4 29.4 15.7 2.1

STATEWIDE 15860 2.4 478.9 32.4 8.6 No known records of illness can be attributed to radon. However, Rindge residents should be aware that

radon is present. Houses with granite and dirt cellars are at increased risk

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (28)

Rindge Hazard Mitigation Plan- 2007

21

MAN MADE HAZARDS- DAMS- LOW RISK The State of New Hampshire classifies dams into the following four categories: NM – Non-menace S – Significant hazard Blank- Non-Active L – Low hazard H – High Hazard Generally, all Class H dams need to have Emergency Action Plans, and most Class S dams also require them. According to the Department Of Environmental Services Dam Bureau, there are four Class S dams and three Class H dams in Rindge, for which an Emergency Action Plan is required and an inundation zone has been delineated.

Dam # Hazard Name Dam Owner Height(ft) Impound(ac) 203.01 S Lower Damon Reservoir Dam Damon Realty 15 24.5 203.02 L Damon Upper Reservoir Dam Mr. John Hunt 9 49 203.03 L Pearly Pond Dam Pearly Lake Assoc. 7 210 203.04 NM Robbins Pond Dam Mr Fred Dodd 5.98 45 203.05 Robbins Pond Dam Unk. 14 203.06 NM Hale Dam Mr. Ed Stevens 12 1 203.07 Sweeney Dam Unk. 8 203.08 NM Contoocook River IV Mr. Fran Berger 10 0.3 203.09 NM Contoocook River V Mr. Richard Smith 6 1 203.10 S Island Pond Dam Hampshire Country School 16 32 203.11 L Mill Pond Dam Hampshire Country School 20 5 203.12 Miller River Dam Mr. Dallas Norcross 203.13 NM Miller River Dam Mrs. Peregrine White 13 6.5 203.14 Miller River III Dam Stoddard Main Co. 203.15 L Bancroft Reservoir Dam Unk. 15 36 203.16 Converse Meadow Pond Dam Mr. John B. Rice 5 33.2 203.17 Conversville Reservoir Mr. John B. Rice 203.18 S Hubbard Pond NH Water Division 8 187 203.19 Hubbard Pond Inlet Dam Mr. Frank Robbins 203.20 Holding Pond Dam Mr. Frank Robbins 203.21 NM Rugg Pond Dam Huber Gunhild Tibbetts 5 9 203.22 L Crowcroft Pond Dam Cropond Inc. 10 65 203.23 NM Tarbell Brook Dam Ms. Linda Harmon 10 1 203.24 Tarbell Brook Dam Mr. Benton Rice 203.25 Recreation Pond Dam Mr. John B. Rice 203.26 Tarbell Brook Dam Ms. Susan Dickinson 203.27 Toy Shop Dam Mr. A J Wellington 203.28 Grassy Pond Dam Town of Rindge 4 99 203.29 NM Bullet Pond Dam Town of Jaffrey 4 50 203.30 Emerson Pond Dam Unk. 203.31 Emerson Pond Brook Dam Mr. Harris Rice 15 203.32 Emerson Pond Brook Dam Unk. 203.33 Miller River Dam E.I. Wellington 10 203.34 Miller River Dam Unk. 11 203.35 Nameless Brook Dam Unk. 203.36 NM Ice Pond Dam Society for Prot. Of NH Forests 6 2 203.37 Inlet Pond Dam Town of Jaffrey 4 203.38 Miller Pond Dam Unk. 8 203.39 Contoocook Lake Dam BSHN Properties 0.5 203.40 NM Speckhams Dam Mr. Joseph Connolly 6 0.19 203.41 L Stump Pond Dam Hampshire Country School 8 15

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (29)

Rindge Hazard Mitigation Plan- 2007

22

Dam # Hazard Name Dam Owner Height(ft) Impound(ac) 203.42 NM Pool Pond Dam NH DOT 4 144 203.43 Unnamed Stream Dam Unk. 203.44 L Van Dyke Dam Mr. Robert Van Dyke 8 18 203.45 NM Tarbell Brook Dam Mr. Richard Whicker 8 2 203.46 NM Cheshire Marketplace Dam Market Basket, Inc. 9 0.5

Source: Dam information provided by the NH Dam Bureau in 2006 and will be verified by Town officials

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (30)

Rindge Hazard Mitigation Plan- 2007

23

Chapter IV: Assessing Probability, Severity and Risk Estimating Potential Losses

The Committee members completed Risk Assessment Worksheets for all of the types hazards identified in Chapter III. The process involved assigning Low, Medium, or High values (numerically 1, 2 or 3) to each hazard type for its possible impact to Human, Property, and Business factors. (A score of zero was given if the hazard was non-applicable). To assess probability, a 1, 2, or 3 value was assigned to each hazard type with respect to the likelihood that the hazard would occur in the next 25 years. The Severity was calculated by determining the average of the Human, Property, and Business impacts. Risk was calculated by multiplying severity by probability. Low-Medium-High risk was assigned as shown below. Estimated potential losses and areas of greatest risk are included in the table below.

0-1.9- Low 2.0-3.9- Low-Med 4-5.9- Med 6-7.9- Med-High 8-9- High Human Impact

Property Impact

Business Impact Probability Severity Risk

Probability of death or

injury

Physical Losses and damages

Interruption of Service

likelihood this will occur in 25

years

Avg. of Human/

Property/ Business

Severity x Probability (Relative Threat)

Risk

Estimated Potential Losses7

(Dollars)

Areas of Greatest

Risk

Flooding 1 3 2 2 2.00 4.00 Med n/a Along rivers Riverine Flooding 0 2 1 1 1.00 1.00 Low n/a Near

waterbodies Drought 0 1 1 1 0.67 0.67 Low n/a Town-wide

Extreme Heat 1 0 1 1 0.67 0.67 Low n/a Elderly, Town-wide

Wild Fire 3 3 2 2 2.67 5.33 Med n/a Forested areas

Lightning 2 3 2 3 2.33 7.00

Med-High

n/a Town-wide;

High Elevation,

power lines

Tornado 2 3 3 1 2.67 2.67 Low-Med 11,047,997 Town-wide

Hurricane 2 3 3 2 2.67 5.33 Low-Med 13,809,372 Town-wide

Earthquake 2 2 2 1 2.00 2.00 Low-Med 110,479,968 Town-wide

Subsidence 1 1 1 1 1.00 1.00 Low n/a US 202 @ Jaffrey TL

Radon 1 2 0 3 1.00 3.00 Low n/a Town-wide

Severe Wind 2 3 2 3 2.33 7.00 Low-Med n/a Town-wide

Extreme Winter

Weather 2 3 2 3 2.33 7.00 Low-Med

n/a Town-wide;

High Elevation

Areas

Avalanche 1 1 1 0 1.00 0.00 Low n/a Town-wide

HazMat Spills

3 3 3 3 3.00 9.00 Low-Med

n/a Fuel depots, gas stations,

transfer station

Dam Failure 1 2 1 2 1.33 2.67 Low n/a Hampshire School Dam

Landslides 1 1 1 0 1.00 0.00 Low n/a Along steep slopes

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (31)

Rindge Hazard Mitigation Plan- 2007

24

CHAPTER V CRITICAL FACILITIES

A Critical Facility is defined as a building, structure, or location which:

• Is vital to the hazard response effort • Maintains an existing level of protection from hazards for the community • Would create a secondary disaster if a hazard were to impact it

Critical Facilities Within Hazard Areas Hazards identified in this plan are regional risks and, as such, all critical facilities fall into the hazard area. The exception to this is flooding. There are three identified critical facilities that fall within the 100-year floodplain. These are Camp Crescent on Monomonac Lake, Advent Church (off South Woodbound Rd) and the Little Michigan sewage service zone on Lake Contoocoock. The Critical Facilities List for the Town of Rindge has been identified through discussions of the Hazard Mitigation Committee. Rindge's Hazard Mitigation Committee has divided this list of facilities into four categories. The first category contains facilities needed for Emergency Response in the event of a disaster. The second category contains Non-Emergency Response Facilities that have been identified by the Committee as non-essential. These are not required in an emergency response event, but are considered essential for the everyday operation of Rindge. The third category contains Facilities/Populations that the Committee wishes to protect in the event of a disaster. The fourth category contains Potential Resources, which can provide services or supplies in the event of a disaster. The Critical Facilities Map at the end of this Plan identifies these facilities. A table at the end of this section identifies critical facilities located in potential hazard areas. Category 1 - Emergency Response Services: The Town has identified the Emergency Response Facilities and Services as the highest priority in regards to protection from natural and man-made hazards. 1. Emergency Operations Center

Rindge Police and Fire Station - 150 Main Street

2. Fire Station 150 Main Street

3. Police Station 158 Main Street

4. Emergency Fuel Facilities

State Highway Garage (NH Department of Transportation Shed) on Rt. 119 5. Emergency Electrical Power Facility

Emergency Generator at Police Station (158 Main Street)

6. Emergency Shelters Rindge Memorial School and Franklin Pierce University.

7. Dry Hydrants - Fire Ponds - Water Sources

Numerous locations; see Critical Facilities Map at back of Plan

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (32)

Rindge Hazard Mitigation Plan- 2007

25

8. Primary Evacuation Routes US 202 NH 119

9. Bridges Located on Primary Evacuation Routes

US 202, one bridge located on Jaffrey Town Line

10. Town Garage/Transfer Station Same as Highway Garage, located at 113 Main St.

11. Communications Keene Mutual Aid dispatch system Cheshire Sheriff’s department dispatch system State of New Hampshire Troop C dispatch system

12. Hospitals Cheshire Medical Center (to the west in Keene) Monadnock Community Hospital (located to the east in Peterborough) Hospital in Gardner, MA (located to the South)

13. Helicopter Landing Sites

Parking Lot of Cathedral of the Pines (located off of NH 119) Franklin Pierce University athletic fields

14. Water & Sewer Departments/Utilities

Little Michigan area of town, located on the North Shore of Poole Pond, served by the Town of Jaffrey Sewer System.

Category 2 - Non Emergency Response Facilities: The town has identified these facilities as non-emergency facilities; however, they are considered essential for the everyday operation of Rindge. 1. Water Supply

Lakes and Ponds (Poole Pond, Pearly Lake, Grassy Pond, Bullet Pond, Lake Monomonac, and various other surface waters)

2. Sewer Infrastructure

Private Sewer System for Franklin Pierce University (owned and operated by the college) 3. Problem Culverts

Due to the large quantities of water throughout the Town, there are many potential problem culverts maintained by the Town and the State. The Highway Foreman identified the following:

• Robbins Rd. to Winchendon • East Monomonac Rd. to

Winchendon • Abel Rd. to Fitzwilliam

• Fitzgerald Road • Old New Ipswich Road • Wellington Rd. to US 202 • Hampshire Road

4. Transfer Station Same as Highway Garage, located at 113 Main St.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (33)

Rindge Hazard Mitigation Plan- 2007

26

5. Secondary Evacuation Routes • Forristall Rd. and Middle Winchendon Rd. • Cathedral Rd. into Jaffrey • Main St. onto US 202 South to Winchendon

6. Bridges on Secondary Evacuation Routes None Category 3 - Facilities/Populations to Protect: The third category contains people and facilities that need to be protected in event of a disaster. 1. Special Needs Populations

The Hampshire Country School is located in Rindge near the New Ipswich Town Line, on Mill Pond. The School is dedicated to young boys with Asperger’s Syndrome and other non-verbal learning disabilities, the school usually houses 25 children. Many residents in Rindge may have disabilities or impairments which make them a priority in the event of a disaster. List should be available at the Emergency Operations Center and may include:

Oxygen-dependent people People on a lifeline People assisted by Home Health Shut-ins and disabled Mentally challenged Elderly Hearing impaired Sight impaired

2. Recreation Areas

Memorial School Athletic Fields Town Recreational Fields (ball fields, tennis courts, soccer fields) Meeting House and common Franklin Pierce University Athletic Fields Cathedral of the Pines Camp Wildwood (Mass. Audubon) on Old New Ipswich Road

3. Schools Rindge Memorial School Meeting School Heritage Christian School Franklin Pierce University

4. Day Cares

Private daycare facilities are located at the following locations Cathedral Road Hubbard Hill Road

5. Churches Meeting House Congregational Church (Payson Hill Rd.) West Rindge Methodist Church/Vineyard Church (US 202) Monadnock Full Gospel Church (US 202) North St. Baptist Church Advent Lutheran Church (US 202 & Corner County Road)

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (34)

Rindge Hazard Mitigation Plan- 2007

27

6. Historic Buildings/Sites Meeting House (Payson Hill Rd.) Cathedral of the Pines (Cathedral Rd.) Historic Society Museum (School St.)

7. Major Employment Centers

Franklin Pierce University Cheshire Market Place Wal-Mart/Hannaford’s Plaza Dunkin Donuts/KFC- Phase 10 Plaza Fogg’s Mini Mart Plaza Sears Drive Sepco Building on NH 119 (10-12 businesses) Canterbury Square retail on NH 119/Main St. Lilly’s on the Pond on NH 202 East Rindge Village Atlas Fireworks (various businesses)

8. Apartment Complexes

Franklin Pierce University (dormitories) Hasbrook Apartments (Payson Hill Rd.) Meadow View (Taggart) Apartments (Meadow View Rd.) Cromwell Court Condominiums (US 202) Carriage House Apartments Renaissance Senior Housing

9. Post Office

The Post Office is located on Route 119 10. Hazardous Material Storage

Atlas Fireworks store (multi-tenant building) Fogg’s Corner - Diesel, Propane, Heating Oil Franklin Pierce Sewage Treatment Plant Fireworks storage area off of US 202 Gas Station on NH 119 just west of Payson Hill Rd. Gas Station on NH 119 west of Payson Hill Rd. North of the Border boat landing on Lake Monomonac Wal-Mart (paints, cleaning chemicals, etc.)

Category 4 - Potential Resources: Contains facilities that provide potential resources for services or supplies. 1. Food Food Pantry Woodbound Inn Wal-Mart (sundries store on US 202) Market Basket (Grocery Store on US 202) Hannaford’s KFC/TacoBell Pizza Haven North of the Border

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (35)

Rindge Hazard Mitigation Plan- 2007

28

2. Water Numerous locations - see Critical Facilities Map at back of Plan

3. Hospitals/Medical Supplies

Cheshire Medical Center (to the west in Keene) Monadnock Community Hospital (to the northeast in Peterborough)

Medical Facilities Located in Keene, Jaffrey or Peterborough Helicopter medi-vac from DART and UMass Henry Hayward Hospital in Gardner, MA

4. Gravel Pits

Rindge Sand and Gravel Kohl Morgan’s Gravel Digz Excavating Franklin Pierce University Gravel Pit Red White Gravel Pit - Inactive Christian Outreach

5. Gas Highway Garage (113 Main St. ) NH DOT maintenance shed on NH 119 Fogg’s Corner (Diesel & Gas) Gas stations on NH 119 west of Payson Hill Rd. 6. Heating Fuel Fogg’s Corner (US 202 & NH 119) has storage tanks 7. Building Material and Heavy Equipment Suppliers 202 Trucking - Heavy Equipment Lake Shore Landscaping - Heavy Equipment Van Dyke’s Heavy Equipment NH DOT Shed on NH 119 Diggs Excavating (Sepco Building) 8. Miscellaneous Resources

Emergency Broadcast & Television: WMUR Potential Emergency Shelter at Franklin Pierce University Amateur Radio Emergency Service: Craig Clark Hazardous Material Response Trailer from Southwest New Hampshire Mutual Aid Transportation: Buses - Franklin Pierce University

School bus driver’s homes Laidlaw in Peterborough

Trucks -Local Contractors, National Guard, Keene Beds, Cots, Blankets: National Guard

Red Cross Keene Mutual Aid Trailer with cots, beds, and blankets

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (36)

Rindge Hazard Mitigation Plan- 2007

29

Additional Information The Hazard Mitigation Committee identified several campgrounds and trailer parks which should also be included in this list. They include: Monadnock Park Trailer Homes Camp Wildwood Toahnipi Campground

Crescent Beach Campground Camp Joy Woodmore Campground

Critical Facilities and Evacuation Routes Potentially Affected by Hazard Areas

Hazard Type Hazard Area Critical Facilities Affected Evacuation Routes

Affected

Flooding Contoocoock Lake Advent Church (off South Woodbound Rd)

US 202 (northern section into Jaffrey)

Contoocoock Lake Little Michigan (served by public sewage)

Lake Monomonac Crescent Beach Campground

Dams on Mill Creek none affected NH 119

Wildfire All forested areas, nature conservancies Many camp grounds none

Lightning US 202 south Retail stores in US 202 corridor None Subsidence Jaffrey Town Line none affected US 202

Hazardous Materials Northern US 202 (fireworks store and storage facility) None US 202

Hazardous Materials Gas stations on NH 119 None US 202/NH 119

Hazardous Materials Franklin Pierce University Waste Treatment Plant

All Franklin Pierce emergency facilities none

(Critical Facilities Map Located In Back of Plan)

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (37)

Rindge Hazard Mitigation Plan- 2007

30

CHAPTER VI: EXISTING MITIGATION STRATEGIES & PROPOSED IMPROVEMENTS This step involves identifying existing mitigation strategies and Town programs and evaluate their effectiveness. This section outlines those programs and recommends improvements to ensure the highest quality emergency services possible.

Existing Mitigation Strategies and Proposed Improvements

Existing Protection Description

/Area Covered

Responsible Local Agent

Effectiveness

Proposed Improvements

School Evacuation Plan - Rindge Memorial School and Franklin Pierce University have evacuation plans in place. The other schools in town have small plans in place. The schools are primarily responsible for having a plan in place and conducting at least 10 fire drills every year. The fire department provides feedback on the plans and the drills

Fire and Emergency Evacuation

Plan

Schools Good

Rindge Memorial and Franklin Pierce have in-

depth plans. Other schools have smaller plans. Fire

Dept. comments on plans.

Town-Adopted Building Code - Rindge maintains a code enforcement officer and has adopted provisions of the NH Life Safety Code and the NH State Building Code. Rindge has also adopted provisions of the International Building Codes for one and two family residential structures. Current program is working. Operate under State Building Codes RSA 155-A with increased restrictions & International Residential Building Codes

Whole Town

Code Enforcement

Officer /Selectmen

Good

Develop comprehensive and coordinated fire

sprinkler standard since NFPA contains only minimal standards.

Develop fire protection ordinance to have a

locally defined set of standards

Code Enforcement Officer - The Fire Chief and Code Enforcement Officer jointly enforce building codes and review building permit applications. The Code Enforcement Officer also enforces zoning ordinances and reviews applications.

Enforces Building Code and Zoning

Ordinance Town-Wide

Fire Chief and Code

Enforcement Officer

Fair

The Fire Chief has expressed that in the case

of big-box stores, it is difficult to determine whether adequate fire

suppression capacity is being met without having access to

complete building plans and list of materials (fuel load) to be contained in

building Emergency Management Plan - The town’s Emergency Management Plan, adopted in 1994 establishes protocols for all town departments in the event of an emergency. The plan has since been updated

Town-Wide Emergency Response

Plan

Emergency Management

Director Good Updated as required

Health Officer - The town has a Health Officer and a Deputy Health Officer. The Health Officer provides mostly informational resources related to septic systems, wells, etc. These positions are appointed by the town.

Inspects

Failed Septic Systems,

Wells, etc.

Health Officer, and

Deputy Health Officer

Fair

Health Officer is only part time volunteer. .Additional

capacity needed to deal with threats to recreational

lakes.

Fire Inspector - The Fire Chief annually inspects all commercial, rental, and foster home buildings. Single family homes are inspected on a per-request basis

Commercial, rental &

foster homes Fire Chief Good Annual inspections

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (38)

Rindge Hazard Mitigation Plan- 2007

31

Existing Protection Description

/Area Covered

Responsible Local Agent

Effective-ness

Recommended Changes - Actions

Emergency Back-up Power Program - The Fire and Police Departments have a generator for emergency back-up power at the Fire Station. Town Hall is being updated with a new backup system, and the Highway Department does not have any back-up power but would like to eventually receive it

Fire and Police

Department have backup generators.

Fire Chief Selectmen Fair

Project underway to provided backup power to Town Hall, Franklin Pierce University and Rindge Memorial as part of Emergency Shelter development. Phone system does not work in Town Hall when power is out.

Local Road Design Standards - Standards are set by the planning board, Highway Department and the Selectmen to ensure a constant construction benchmark

Design Specs/Dead

End & Cul de Sacs/Town

Existing Road Upgrade

Specs

Hwy Dept., Selectmen, & Planning

Board

Good

Design Specs/Dead End & Cul de Sacs/Town

Existing Road Upgrade Specs

Local Bridge Maintenance Program - Bridges located on State routes in Rindge are inspected annually and maintained by the NH Department of Transportation. Guidelines and schedules for annual upkeep are established by NH DOT. Rindge does not have many locally owned bridges, but those that fall in the local jurisdiction do receive general repairs on an as-needed basis

NH DOT Inspects and Does Work Town-wide

NHDOT, Highway

Department Good none

Local Road Maintenance Program - A road committee oversees road maintenance needs on a monthly basis; using a roadway surface management system, projects are prioritized and entered into a maintenance program.. Rindge allocates approximately $280,000 each year to various roadway projects, such as resurfacing, culvert replacement and repair

Local roads/Town

Wide

Highway Department Good

Use roadway management system to allocate $280,000

annually to maintenance and rehabilitation

Tree Maintenance Program - The Highway Department does 90% of the removal of hazardous trees along the roadside

Town Wide Highway Department Good Remove dead trees along

roads.

Winter Storms Operations Plan - The Fire Department, Police Department, and Highway Department coordinate during winter storms to keep the local highways and roads open and accessible. Radio communication provides the link that allows for crews to patrol various sections of town simultaneously and to provide 24-hour patrols during severe weather. This setup works well for the town

Whole Town

Fire, Police, and

Highway Departments

Good none

Town Master Plan - A Guidance document to ensure that overall development in town is sustainable, meeting the needs of the citizens by setting forth steps and guidelines for a sound living environment through well planned growth. The Planning Board and Planning Department are currently working on a major update of the Master Plan

Update 2001/Town

Wide

Planning Board,

Planning Department

Good Update as needed

Steep Slopes Protection - The Town has some Steep Slopes requirements in the Driveway Regulations. Town-Wide

Code Enforcement

Officer, Planning

Board

Good Improve current regulations

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (39)

Rindge Hazard Mitigation Plan- 2007

32

Existing Protection Description

/Area Covered

Responsible Local Agent

Effective-ness

Recommended Changes - Actions

Mutual Aid - Provides assistance to all aspects of Rindge’s Emergency Management Services in town. Southwest New Hampshire Fire Mutual Aid (SWNHFMA) and the Cheshire County Sheriff’s Department provide mutual aid to Rindge. SWNHFMA serves 83 cities and towns and the Cheshire County Sheriff’s Department serves all communities within Cheshire County. The Sheriff’s Department also provides dispatching services for the Police Department. Other Mutual Aid - Rindge has an agreement with New Ipswich for police services and road maintenance. They also have an agreement in place with Jaffrey for road maintenance for some roads in Little Michigan area of the Town

Provides assistance to all aspects of

Rindge Emergency

Management Services/ Highway

Department/whole town

Fire Chief, Police Chief, Emergency

Management Director, Highway

Department and

Selectmen

Good

Fire Dept. – SWNHFMA coordinates mutual aid with 83 regional communities; Police Dept. – Cheshire County Sheriff’s Dept. provides service to all

Cheshire County communities;

Highway Dept. has verbal agreements with

neighboring towns of New Ipswich and Jaffrey, PD

with town of New Ipswich.

Fire Dry Hydrant Management Plan - This designates a maintenance schedule for the local dry hydrants used by the Fire Department for water supply for fire prevention and suppression. The Fire Department is responsible for this plan, and they take advantage of low water opportunities to perform the work or install new hydrants. The Highway Department is responsible for keeping the hydrants accessible. Each hydrant is maintained twice a year.

Location and Maintenance

of Dry Hydrants

Fire Chief Fair

This plan works well, but the Fire Department would like to have more

hydrants installed

Hazardous Materials Spill Prevention Control and Counter Measures Plan - This plan is on hand with the Fire Department in the event that there is an incident. Personnel in the Fire Department and Highway Department receive regular training for handling hazardous materials spills. SWNHFMA’s Haz-Mat Team is called upon in the event of a major spill. This plan works excellently

Fire, Police, and Highway Departments

Fire Chief, Highway

Department &

SWNHFMA

Good

Plan is held by Fire Chief. Departments receive

frequent training. SWNHFMA HazMat Team

provides backup.

Town Warning System - The town does not have a Town Warning System. The town would like to have a reverse 911 System. There is currently one siren in town, and one siren at the Wildwood Camp that signals when a camper has gone missing

Siren located at Fire Hall, another siren

located in Wildwood

Camp.

Fire and Police

Departments Poor

Create Reverse 911 system, update siren and provide education on its meaning.

Erosion and Sedimentation Plan - E&S plans are established by the state for erosion and sediment control. The Town of Rindge has established stormwater controls more stringent than those of the State for commercial and multi-family developments. The Code Enforcement Officer is responsible for enforcement, but this is difficult due to the lack of continued on-the-job training in environmental sciences

State & local guidelines for roads and soil erosion/Whol

e town

NH DES, Planning Board, &

Code Enforcement

Officer

Good

More training required for Code Enforcement officer in areas of environmental

sciences.

Wetlands Protection - The Town has adopted a Wetlands Ordinance that imposes certain restrictions on building within 50’ of a wetland

Town Wide

NH DES; Code

Enforcement Officer, Planning

Board

Good none

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (40)

Rindge Hazard Mitigation Plan- 2007

33

Existing Protection Description

/Area Covered

Responsible Local Agent

Effective-ness

Recommended Changes - Actions

Town Radio System - The existing radio system for emergency responders includes analog and digital radios for the Police Department and analog and digital radios for the Fire and Highway Departments. SWNHFMA provides town-wide alert to emergency responders in the event of an incident. The system works well overall

Town wide Frequency

Police, Fire, and

Highway Departments

Average Town is seeking to acquire second frequency

Shoreland Protection- Designates a protective buffer along all surface waters in town. No local ordinance enacted. Town relies on the State’s Shoreland Protection Act

All surface waters

Code Enforcement Officer, NH

DES

Good none

Town-Sponsored Safety Awareness Program - The Fire Department provides annual fire prevention and health safety trainings classes and presentations at the local schools. Local residents may request a fire inspection of their residences if they wish

Town-Wide Safety

Training

Fire Department Good none

Ambulance Service - The Town currently has ambulance service from Jaffrey/Rindge Memorial. The service provided has been improving and adequately serves the needs of the community

Jaffrey/Rindge Memorial Ambulance Service –

Town wide

N/A Good none

Radiological Evacuation Plan - Town does not have a radiological evacuation plan since it is located outside the 10 mile Vermont Yankee emergency zone. The town has received radiological monitors, but has never received training for them

None Emergency

Management Director;

Poor

Training on use of radiological meters and inclusion of evacuation

routes

Preliminary Prioritization The Rindge Hazard Mitigation Team ranked each of the above Mitigation Strategies and Town programs, as shown in the following table, for its effectiveness related to the critical evaluation factors listed below. A numerical value of 3, good (or yes), was determined as the highest rating with 2 corresponding with average (or maybe) and 1 as poor (or no). Actions of highest priority are those with the highest total ranking score. The highest possible score is 42. • Ability to reduce disaster damage • Contributes to other community goals • Ability to benefit the environment • Need for regulation • Ability to save/protect historic structures • Ability to achieve other community objectives • Ability for quick implementation

• Level of social acceptability • Technical feasibility/potential success • Administratively feasible • Level of political acceptability • Legal authority to implement • Positive cost/benefit review for local economy • Whether there are environmental approvals required

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (41)

Rindge Hazard Mitigation Plan- 2007

34

Recommended Improvements Ranking Rank Recommended

Improvements Legend: 3 = Good 2 = Average 1 = Poor *If no approvals are required, rank is 3. If approvals are, rank is 1. D

oes i

t red

uce

disa

ster

da

mag

e?

Doe

s it c

ontr

ibut

e to

oth

er

goal

s?

Doe

s it b

enef

it th

e en

viro

nmen

t?

Doe

s it m

eet r

egul

atio

ns?

Will

his

tori

c st

ruct

ures

be

save

d or

pro

tect

ed?

Doe

s it h

elp

achi

eve

othe

r co

mm

unity

obj

ectiv

es?

Cou

ld it

be

quic

kly

impl

emen

ted?

Is it

Soc

ially

acc

epta

ble?

Is it

Tec

hnic

ally

feas

ible

an

d po

tent

ially

succ

essf

ul?

Is it

Adm

inis

trat

ivel

y w

orka

ble?

Is it

Pol

itica

lly a

ccep

tabl

e?

Is th

ere

Leg

al a

utho

rity

to

impl

emen

t?

Cos

t/Ben

efit

Rev

iew

Are

oth

er E

nvir

onm

enta

l ap

prov

als r

equi

red*

?

TO

TA

L

1 Buy additional radio frequencies and 2 repeaters (radio interoperability)

3 3 3 3 1 3 2 3 3 3 3 3 3 3 39

2 More dry hydrants 3 3 3 3 1 3 2 3 3 3 3 3 3 2 38

2 Coordination w/Yankee evacuation (State) 3 3 3 3 1 3 2 3 2 3 3 3 3 3 38

3 Expand regular surface water testing 3 3 3 3 1 3 2 3 2 2 3 3 3 3 37

3 Reverse 911 3 3 2 3 1 3 1 3 3 3 3 3 3 3 37

3 RMS School should have backup power 2 3 2 3 1 3 2 3 3 3 3 3 3 3 37

3 Franklin Pierce Shelter back up power 2 3 2 3 1 3 2 3 3 3 3 3 3 3 37

3 Power back up for Town Hall 2 3 2 3 1 3 2 3 3 3 3 3 3 3 37

4 Radiological training for monitors 2 3 2 3 1 2 2 3 3 2 3 3 3 3 35

4 Public education re: warning signals, cold weather 2 3 2 3 1 3 2 3 2 2 3 3 3 3 35

4 New fire codes for commercial buildings (more stringent sprinklers)

3 3 2 3 1 2 2 2 3 3 2 3 3 3 35

5 Code enforcement –environmental training for health officer

2 3 3 3 1 3 1 2 3 2 1 3 2 2 31

5 Erosion Sediment Control ordinance 2 3 3 3 1 3 2 2 1 1 2 3 2 3 31

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (42)

Rindge Hazard Mitigation Plan- 2007

35

CHAPTER VII MITIGATION STRATEGIES

The Hazard Mitigation Committee held a brainstorming session during the fifth committee meeting. In order to determine mitigation projects, the Committee used the following objectives:

Preventative (Programs & Policies) Training Public Education & Information Engineering Projects Property Protection Structural Projects Equipment Purchases

With these in mind, the Committee reviewed their overall goals and the hazards, both man-made and natural, as identified in Chapter III. The Committee created a list of possible projects from the types of hazards for which Rindge is at risk. These non-prioritized items are in the directory below. A prioritized list and implementation schedule is included in the next chapter. Preventative (Programs/Policies): • Continue mutual aid pacts with surrounding communities to share resources in order to be better

prepared for emergency situations. • Coordinate with state agencies to resolve radio jams of Mutual Aid frequency during Vermont Yankee

drills. • Prepare emergency transportation plan for the evacuation of special needs populations during disaster

events. • Coordinate neighborhood level plans with one town representative designated to each town (preferably

one in which they live). • Compile list of volunteers and private resources (snowmobiles, ATVs, etc…) • Implement Septic System ordinance. • (see Chapter VI for improvements to existing mitigation measures). Training:

• No additional training needed at this time (see Chapter V for improvements to existing mitigation measures).

Public Education & Information: • Detours - Provide the public with information on evacuation procedures, evacuation routes,

and emergency shelters (see also Equipment Purchase). • No additional measures at this time (see Chapter VI for improvements to existing mitigation

measures).

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (43)

Rindge Hazard Mitigation Plan- 2007

36

Engineering: • Provide power back-up for US 202/NH 119 intersection, so that when power goes out, police officers

do not have to be diverted for traffic control. • Provide public sewer around lakes to prevent contamination from septic systems. Property Protection: • Implement sandbag program, whereas materials and tools would be stockpiled at the Highway garage,

and volunteers would be on stand-by to fill and distribute sandbags in case of an emergency. Structural Projects: None at this time. Equipment Purchases: • Purchase portable generators to power homes of special needs population during power outages and to

powers sump pumps. • Purchase portable pumps to pump out flooded basements and houses. • Detours - Acquire cones, barriers, and detour signs to use when roadways are closed (see also Public

Education & Information). • Acquire ATVs (Rhinos) and boats for rescue and forest fire fighting. • Acquire CB & Ham radio for Emergency Operations Center. • Acquire excavator for Public Works department. Preliminary Prioritization The Rindge Hazard Mitigation Team ranked each of the above Mitigation Strategies and Town programs, as shown in the following table, for its effectiveness related to the critical evaluation factors listed below. A numerical value of 3, good (or yes), was determined as the highest rating with 2 corresponding with average (or maybe) and 1 as poor (or no). Actions of highest priority are those with the highest total ranking score. The highest possible score is 42. • Ability to reduce disaster damage • Contributes to other community goals • Ability to benefit the environment • Need for regulation • Ability to save/protect historic structures • Ability to achieve other community objectives • Ability for quick implementation

• Level of social acceptability • Technical feasibility/potential success • Administratively feasible • Level of political acceptability • Legal authority to implement • Positive cost/benefit review for local economy • Whether there are environmental approvals required

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (44)

Rindge Hazard Mitigation Plan- 2007

Mitigation Strategies Ranking

37

Rank New Proposed Mitigation Action

Legend: 3 = Good 2 = Average 1 = Poor *If no approvals are required, rank is 3. If approvals are, rank is 1.

Doe

s it r

educ

e di

sast

er d

amag

e?

Doe

s it c

ontr

ibut

e to

ot

her

goal

s?

Doe

s it b

enef

it th

e en

viro

nmen

t?

Doe

s it m

eet

r egu

latio

ns?

Will

his

tori

c st

ruct

ures

be

save

d or

pro

tect

ed?

Doe

s it h

elp

achi

eve

othe

r co

mm

unity

ob

ject

ives

?C

ould

it b

e qu

ickl

y im

plem

ente

d?

Is it

Soc

ially

a c

cept

able

? Is

it T

echn

ical

ly

feas

ible

and

po

tent

ially

f

l?Is

it A

dmin

istr

ativ

ely

wor

kabl

e?

Is it

Pol

itica

lly

acce

ptab

le?

Is th

ere

Leg

al

auth

ority

to

impl

emen

t?

Cos

t/Ben

efit

Rev

iew

Are

oth

er

Env

iron

men

tal

a ppr

oval

s req

uire

d*?

TO

TA

L

1 Sandbag program (stockpile materials& volunteers) 3 3 3 3 3 3 2 3 3 2 3 3 3 3 40 2 Portable generators for sumps and houses 3 3 2 3 2 3 2 3 3 3 3 3 3 3 39 2 Portable Pumps 3 3 2 3 2 3 2 3 3 3 3 3 3 3 39

2 Detours – Acquire cones, barriers etc. & Public education 3 3 3 3 1 3 2 3 3 3 3 3 3 3 39

3 Conduct survey of residents regarding vulnerability and volunteer opportunities 3 3 1 3 1 3 3 3 3 3 3 3 3 3 38

3 ATV’s (Rhinos) & Boats for rescue 3 3 3 3 1 3 2 3 3 3 3 3 2 3 38 4 Power back up for 119/202 intersection 3 3 2 2 1 3 2 3 3 3 3 3 3 3 37 4 Acquire CB & HAM radio for Emergency Ops Ctr 2 3 2 3 1 3 2 3 3 3 3 3 3 3 37

5 Resolve Mutual Aid radio jams during Yankee drills 3 3 2 3 1 3 2 3 2 2 3 3 3 3 36

5 Emergency Transportation Plan for moving people 3 3 2 3 1 3 2 3 2 2 3 3 3 3 36

5 Neighborhood level plans, with town coordinator designated to each 3 3 2 3 1 3 2 3 2 2 3 3 3 3 36

6 Coordination of volunteers and private resources (snowmobiles, atvs) 2 3 2 3 1 3 2 3 2 2 3 3 3 3 35

6 Securing supplies with retail stores 3 3 1 3 1 3 2 3 2 2 3 3 3 3 35

6 Coordinate School Superintendent w/ FD & PD re: days off & trouble students 2 3 2 3 1 3 2 3 2 2 3 3 3 3 35

7 Implement septic system ordinance 3 3 3 3 1 3 1 2 2 1 2 3 3 3 33 8 Excavator for Public Works 2 3 2 3 1 3 2 2 3 2 2 3 1 3 32

9 Public sewage around lake (such as little Michigan) 3 3 3 3 1 3 1 1 2 1 2 3 2 2 30

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (45)

Rindge Hazard Mitigation Plan- 2007

38

POTENTIAL HAZARD LOCATION MITIGATION ACTIONS The Rindge Hazard Mitigation Committee identified mitigation actions for the locations identified as possible future hazard areas identified in Chapter III. The Potential Hazard Actions Matrix on the following page identifies these proposed mitigation actions. The matrix includes the hazard type (Column 1), location (Column 2), objective (Column 3), risk(s) (Column 4), mitigation actions (Column 5), and comments (Column 6). Mitigation actions identified in the matrix are further considered in Chapter VII, and where determined feasible, have been integrated into the Hazard Mitigation Implementation Schedule. The Hazard Mitigation Committee made it a priority to focus the town’s hazard mitigation efforts on hazards most likely to affect the community. Therefore, some hazards which have the potential to occur town-wide, but are unpredictable in terms of when, where, and how it would affect the community if it did occur, may not have identified mitigation strategies. The Committee agreed that potential mitigation strategies for each hazard type should be further considered during the annual review of the plan. Preliminary Prioritization The Rindge Hazard Mitigation Team ranked each of the above Mitigation Strategies and Town programs, as shown in the following table, for its effectiveness related to the critical evaluation factors listed below. A numerical value of 3, good (or yes), was determined as the highest rating with 2 corresponding with average (or maybe) and 1 as poor (or no). Actions of highest priority are those with the highest total ranking score. The highest possible score is 42. • Ability to reduce disaster damage • Contributes to other community goals • Ability to benefit the environment • Need for regulation • Ability to save/protect historic structures • Ability to achieve other community objectives • Ability for quick implementation

• Level of social acceptability • Technical feasibility/potential success • Administratively feasible • Level of political acceptability • Legal authority to implement • Positive cost/benefit review for local economy • Whether there are environmental approvals required

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (46)

Rindge Hazard Mitigation Plan- 2007

Potential Hazard Actions Matrix

39

Hazard Type Location Objective Risk(s) Mitigation Actions Comments

Riverine Flooding/

Dams

Many dams throughout town

Reduce threat posed by dam breaches Many possible structures

Update dam GIS layer to include all dams. Make official current policy of having PW Director check all dams when

state sends deficiency letters. In Progress

Flooding due to Beaver

Dams

All lakes and streams in town

Reduce flooding threat posed by beaver dams.

Medium-High risk to many lakefront structures and roads

Continue catch and release program to control beaver populations. In Progress

Flooding Old New Ipswich road

Reduce annual threat to driver safety, access to homes, and access

to evacuation routes caused by potential flooding on the road.

Medium risk to culvert and road Fix the culvert Place project on

CIP

Wildfires All conservation

lands and property on Current Use

Reduce annual threat of forest fire by reducing fuel load through

program of active forest management

Medium-High risk to various properties in and around forests

Institute forest management plans for properties under conservation

Conservation Commission should be in charge of this

item

Hazardous Materials

Fireworks storage at construction site on

US 202 North Secure site to prevent casualties Medium-High risk of personal

injury Ask property owner to add fencing around storage of

explosives

Fire chief should have informal conversation

w/property owner

All fuel stations in town

Prevent spills of fuels into wetlands and groundwater

Medium risk to the drinking water supply

Require on site booms and spill prevention measures as well as training for employees and frequent inspections

Drought Town-wide n/a Low-Medium This town-wide issue is unpredictable in terms of when,

where, and how it would affect the community. No mitigation strategies are proposed at this time.

Extreme Heat Town-wide n/a Low This town-wide issue is unpredictable in terms of when,

where, and how it would affect the community. No mitigation strategies are proposed at this time.

Radon Air/Water Town-wide n/a Low

This town-wide issue is unpredictable in terms of when, where, and how it would affect the community. No

mitigation strategies are proposed at this time.

Tornado Town-wide n/a Med-High This town-wide issue is unpredictable in terms of when,

where, and how it would affect the community. No mitigation strategies are proposed at this time.

Subsidence US 202 North n/a Low risk to roadway US 202 is a state maintained road. Subsidence and drainage issues are well known to NH DOT. No

mitigation strategies are proposed at this time.

Hurricane Town-wide n/a Medium This town-wide issue is unpredictable in terms of when,

where, and how it would affect the community. No mitigation strategies are proposed at this time.

Earthquakes Town-wide n/a Medium This town-wide issue is unpredictable in terms of when,

where, and how it would affect the community. No mitigation strategies are proposed at this time.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (47)

Rindge Hazard Mitigation Plan- 2007

Potential Hazard Actions Matrix

40

Hazard Type Location Objective Risk(s) Mitigation Actions Comments

Severe Wind/ Downburst Town-wide n/a Low

This town-wide issue is unpredictable in terms of when, where, and how it would affect the community. No

mitigation strategies are proposed at this time.

Lightning Strikes Town-wide n/a Med-High

This town-wide issue is unpredictable in terms of when, where, and how it would affect the community. No

mitigation strategies are proposed at this time.

Extreme Winter

Weather

Franklin Pierce University Road

Prevent a potential life safety issue due to drifting snow across roadway. Low

Replant landscaping along roadway as indicated in siteplan of new condominiums. Currently, an ineffective snow

fence is being placed by FP.

Negotiation between town and

college.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (48)

Rindge Hazard Mitigation Plan- 2007

Potential Hazards Actions Ranking

41

Rank New Proposed Mitigation

Action Legend: 3 = Good 2 = Average 1 = Poor *If no approvals are required, rank is 3. If approvals are, rank is 1.

Doe

s it r

educ

e di

sast

er

dam

age?

Doe

s it c

ontr

ibut

e to

oth

er

goal

s?

Doe

s it b

enef

it th

e en

viro

nmen

t?

Doe

s it m

eet r

egul

atio

ns?

Will

his

tori

c st

ruct

ures

be

save

d or

pro

tect

ed?

Doe

s it h

elp

achi

eve

othe

r co

mm

unity

obj

ectiv

es?

Cou

ld it

be

quic

kly

impl

emen

ted?

Is it

Soc

ially

acc

epta

ble?

Is it

Tec

hnic

ally

feas

ible

an

d po

tent

ially

succ

essf

ul?

Is it

Adm

inis

trat

ivel

y w

orka

ble?

Is it

Pol

itica

lly a

ccep

tabl

e?

Is th

ere

Leg

al a

utho

rity

to

impl

emen

t?

Cos

t/Ben

efit

Rev

iew

Are

oth

er E

nvir

onm

enta

l ap

prov

als r

equi

red*

?

TO

TA

L

1 Beaver control program 3 3 3 3 3 3 3 2 3 3 2 3 2 3 39

2 Fuel spill containment booms, training, and inspection of gas stations

3 3 3 3 1 3 2 3 2 3 3 2 3 3 37

2 Fix Culvert on Old New Ipswich Road 3 3 2 3 1 3 3 3 3 3 3 3 1 3 37

3 Dam inspection policy 3 2 2 3 2 2 3 3 3 3 2 3 1 3 35

4 Forest Management to prevent forest fires 3 3 3 3 1 3 1 1 2 2 2 3 2 3 32

5 Snowfencing/landscaping to prevent white-outs on road

2 2 3 3 1 2 1 3 3 2 2 3 1 3 31

6 Security fence around explosive storage area 3 1 3 3 1 1 1 3 2 2 3 2 2 3 30

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (49)

Rindge Hazard Mitigation Plan- 2007

42

CHAPTER VIII: PRIORITIZED IMPLEMENTATION SCHEDULE AND ACTION PLAN

Summary of Critical Evaluation The Rindge Hazard Mitigation Committee reviewed each of the actions identified in the Summary of Recommended Improvements in Chapter VI, as well as mitigation strategies from the brainstorm and Potential Hazard Actions Matrix in Chapter VII using the following factors to prioritize mitigation projects:

• ability to reduce disaster damage • social acceptability • ability to complete or be combined w/other actions • technical feasibility / potential

success • impact on the environment • administrative workability • ability to meet regulations • political acceptability • ability to save or protect historic structures • legal implementation • ability to meet other community objectives • cost/benefit review • the duration of its implementation period • environmental compatibility

An additional factor that is not considered here but should be considered by the Committee on a project-by-project basis is the ability to find funding. Implementation Schedule and Action Plan The Rindge Hazard Mitigation Committee developed an action plan that outlines who is responsible for implementing each of the prioritized strategies determined in the previous chapters, as well as when and how the actions will be implemented. The following questions were asked to develop an implementation schedule for the identified priority mitigation strategies: WHO? Who will lead the implementation efforts? Who will put together funding requests and applications? WHEN? When will these actions be implemented, and in what order? HOW? How will the community fund these projects? How will the community implement these projects? What resources will be needed to implement these projects? Each strategy’s total score from the ranking process is included in the table. As additional information becomes available regarding project leadership, timeline, funding sources, and/or cost estimates, the Plan will be reviewed and amended accordingly.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (50)

Rindge Hazard Mitigation Plan- 2007

43

PRIORITIZED IMPLEMENTATION SCHEDULE (ACTION PLAN)

IMPLEMENTATION STRATEGY FOR PRIORITY MITIGATION ACTIONS

The Rindge Hazard Mitigation Committee created the following prioritized schedule for implementation:

Mitigation Action

Who (Leadership)

When (Deadline)

How (Funding Source)

Cost (Estimated)

Chapter VI, Recommended Improvements:

Buy additional radio frequencies and 2 repeaters (radio interoperability) Police Chief Ongoing

Applied from grant from Homeland Security, waiting

for FCC

$5-$10,000 each $90/year/frequency for 5

years

More dry hydrants Fire Chief/EMD Ongoing, 2/year 12 new hydrants total DF Operations line item $1,000 each

Coordination w/Yankee evacuation (State)Fire Chief/EMD

Coordinate w/State Representative, BOEM Field

Reps

ASAP N/A $0

Expand regular surface water testing Health Officer and Planning

Department, coordinate w/Lake Associations

Summer/Spring 2007 Town Funds/Associations $2,000/year $100/test x 20/year

Reverse 911 Police Department 5 years Grant/Town Match Part of County System $10,000+

RMS School should have backup power Principal & EMD November Budget Process Town/School grants & budget $60-$70,000

Franklin Pierce Shelter back up power EMD & Franklin Pierce Emergency Management

Committee

Part of overall FP plan due Dec. 31st, 2006

Implement over 3-4 years Town & College Grants $150-$200,000

Power back up for Town Hall Town Administrator & EMD 1 year 50/50 Town/Grant $32,000 Radiological training for monitors EMD End of Year N/A $0 Public education re: warning signals, cold weather

EMD/Town Administrator/Schools 1 Year Emergency Management

Line Item $500

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (51)

Rindge Hazard Mitigation Plan- 2007

44

IMPLEMENTATION STRATEGY FOR PRIORITY MITIGATION ACTIONS CON’T

MITIGATION ACTION

WHO (LEADERSHIP)

WHEN (DEADLINE)

HOW (FUNDING SOURCE)

COST (ESTIMATED)

New fire codes for commercial buildings (more stringent sprinklers)

Fire Chief & State Fire Marshal Town Meeting N/A $0

Code enforcement –environmental training for health officer Town Administrator 3-5 Years N/A $35,000/year

Erosion Sediment Control ordinance Town Planner Town Meeting N/A $0 Chapter VII – Mitigation actions

Sandbag program (stockpile materials & volunteers) Public Works Director Town Meeting State supply of sandbags,

Town Funded $500

Portable generators for sumps and special needs populations

Fire Chief/Director of Public Life and Safety

Acquire 2/year over 3 year period

Town Funds, State Grants, Public Donations

$750/Generator $4,500 Total

Portable Pumps for Basements and Buildings Public Works Director 1/year over 2 years Town Funds/Grants $1,500 each

$3,000 Total

Detours – Acquire cones, barriers etc. & Public education PD, FD, and Public Works Ongoing (acquire

piecemeal)

Town Funds/Grants Check w/New Ipswich on

how they got theirs $1,500

Conduct survey of residents regarding vulnerability and volunteer opportunities

Town Administrator & Planning Director ASAP Emergency Line Item $300

ATV’s (Rhinos) & Boats for rescue FD & PD One Year Rhino – Grant

Boat – Fundraiser through Mondadnock Fire Chiefs

$35,000 Boat $10,000 Rhino

Power back up for 119/202 intersection Police Chief End of Year DOT & Town $5,000 Acquire CB & HAM radio for Emergency Ops Center EMD Town Meeting Town $5,000

Resolve Mutual Aid radio jams during Yankee drills FD & PD ASAP N/a N/A

Emergency Transportation Plan for moving people EMD ASAP Existing Funds Unknown

Neighborhood level plans, with town coordinator designated to each

EMD & Neighborhood Associations 1-2 years Existing Funds Unknown

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (52)

Rindge Hazard Mitigation Plan- 2007

45

IMPLEMENTATION STRATEGY FOR PRIORITY MITIGATION ACTIONS CON’T

MITIGATION ACTION

WHO (LEADERSHIP)

WHEN (DEADLINE)

HOW (FUNDING SOURCE)

COST (ESTIMATED)

Coordination of volunteers and private resources (snowmobiles, atvs) EMD After Surveys

6 months N/A Minimal

Securing supplies with retail stores EMD 1 Year N/A $0 Coordinate School Superintendent w/ FD & PD re: days off & trouble students PD & School Principal Ongoing N/A $0

Implement septic system ordinance Health Officer/Town Planner Town Meeting N/A $0 Excavator for Public Works Public Works Director 5+ Years CIP Town $150,000 Public sewage around lake (such as little Michigan) Town Planner/health Officer 15+ Years Bonds ?

Chapter VII – Potential Hazards Action

Beaver control program Public Works Director Ongoing Operating Budget $1,200/year (about $100/beaver)

Fuel spill containment booms, training, and inspection of gas stations

Code Enforcement Officer & Planning Dept. Town Meeting Town Budget N/A

Fix Culvert on Old New Ipswich Road Public Works Director Fall 2007 Road Construction Funds $1,000

Dam inspection policy Town Administrator & Public Works Director Ongoing Part of current work-

Existing funding negligible

Forest Management to prevent forest fires Conservation Commission (w/EMD) Spring 2007 Conservation Funds from

Current Use $8,000

Snowfencing/landscaping to prevent white-outs on road Town Planner Town/Gown Meeting N/A $0

Security fence around explosive storage area Fire Chief ASAP N/A $0

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (53)

Rindge Hazard Mitigation Plan- 2007

46

CHAPTER IX ADOPTION, IMPLEMENTATION, MONITORING & UPDATE

ADOPTION

The Rindge Board of Selectmen adopted the Rindge Hazard Mitigation Plan on ___________. A copy of the resolution can be found at the end of this chapter. Adopted policy addresses the actions for implementation set forth in the chart “Implementation Strategy for Priority Mitigation Actions” in Chapter VII and in the “Monitoring & Updates” sub-section contained in this Chapter VIII. All other sections of this Plan are supporting documentation for information purposes only and are not included as the statement of policy.

MONITORING & UPDATES

Recognizing that many mitigation projects are ongoing, and that while in the implementation stage communities may suffer budget cuts, experience staff turnover, or projects may fail altogether, a good plan needs to provide for periodic monitoring and evaluation of its successes and failures and allow for updates of the Plan where necessary. In order to track progress and update the Mitigation Strategies identified in the Action Plan (Chapter VII), the Town Hazard Mitigation Team will revisit the Rindge Hazard Mitigation Plan annually, or after a hazard event. The Emergency Management Director is responsible for initiating this review and needs to consult with the Board of Selectmen and other key local officials. Changes should be made to the Plan to accommodate for projects that have failed or are not considered feasible after a review for their consistency with the timeframe, the community’s priorities, and funding resources. Priorities that did not make the implementation list, but identified as potential mitigation strategies, should be reviewed as well during the monitoring and update of this Plan to determine feasibility of future implementation. In keeping with the process of adopting the 2006 Rindge Hazard Mitigation Plan, a public hearing to receive public comment on Plan maintenance and updating will be held during the annual review period and the final product adopted by the Board of Selectmen appropriately. The Town of Rindge, NH Hazard Mitigation Plan must be reviewed, revised as appropriate, and resubmitted to FEMA for approval every five years in order to maintain eligibility for Pre-Disaster Mitigation Competitive (PDM-C) and Hazard Mitigation Grant Program project grants.

IMPLEMENTATION OF THE PLAN THROUGH EXISTING PROGRAMS In addition to work by the Hazard Mitigation Committee and town departments, several other mechanisms exist which will ensure that the Rindge Hazard Mitigation Plan receives the attention it requires for satisfactory use. Master Plan Implementation of the Master Plan has been ongoing since its most recent update in 2001. Recommendations from the Rindge Hazard Mitigation Plan will be considered for insertion into future updates of the Master Plan. The Planning Board will consider the Plan as an amendment to its Master Plan. The Local Hazard Mitigation Committee will oversee the process to begin working with the Planning Board to ensure that the Rindge Hazard Mitigation Plan is adopted as a Chapter of the Master Plan.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (54)

Rindge Hazard Mitigation Plan- 2007

47

Zoning Ordinance and Regulations Some of the implementation strategies proposed involve revisions to the Subdivision Regulations and/or the Site Plan Review Regulations as well as the Zoning Ordinance. The Local Hazard Mitigation Committee will oversee the process to begin working with the Planning Board to develop appropriate language for the recommended modifications. Continued Public Involvement On behalf of the Hazard Mitigation Committee, the Emergency Management Director (EMD), under direction of the Board of Selectmen, will be responsible for ensuring that town departments and the public have adequate opportunity to participate in the planning process. Administrative staff may be utilized to assist with the public involvement process. For the yearly update process, techniques that will be utilized for public involvement include: • Provide personal invitations to Budget Committee members; • Provide personal invitations to town department heads; • Post notices of meetings at the Town Office, Library, and local businesses; • Post flyers of the project at the Town Office, Library, and local businesses; and • Submit newspaper articles for publication to the Keene Sentinel and the Monadnock Ledger. A number of Implementation Action items which will be undertaken relate to public education and involvement. Additionally, members of the public including area business owners, schools, communities, and organizations will be invited to participate in the yearly process of updating the Rindge Hazard Mitigation Plan. These outreach activities will be undertaken during the Plan’s annual review and during any Hazard Mitigation Committee meetings the Board of Selectmen calls to order.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (55)

48

CERTIFICATE OF ADOPTION

TOWN OF RINDGE, NEW HAMPSHIRE

BOARD OF SELECTMEN

A RESOLUTION ADOPTING THE RINDGE

HAZARD MITIGATION PLAN WHEREAS, the Town of Rindge established a Committee to prepare the Rindge Hazard Mitigation plan; and WHEREAS, several public planning meetings were held between _____________ and __________ regarding the development and review of the Rindge Hazard Mitigation Plan; and WHEREAS, the Rindge Hazard Mitigation Plan contains several potential future projects to mitigate hazard damage in the Town of Rindge; and WHEREAS, a duly-noticed public hearing was held by the Rindge Board of Selectmen on ________________ to formally approve and adopt the Rindge Hazard Mitigation Plan. NOW, THEREFORE BE IT RESOLVED that the Rindge Board of Selectmen adopts the Rindge Hazard Mitigation Plan. ADOPTED AND SIGNED this _____________

_____________________________________________

Arthur C. Fiorelli Rindge Board of Selectmen

_____________________________________________ Timothy Halliday

Rindge Board of Selectmen

_____________________________________________ Patricia Lang Barry

Rindge Board of Selectmen

ATTEST _____________________________________

,

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (56)

APPENDICES

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (57)

APENDIX A HAZARD DESCRIPTIONS

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (58)

The following list describes hazards that have occurred or have the potential to occur in the Town of Rindge. The descriptions provided are those used in the State of NH Hazard Mitigation Plan (2000). Flooding Floods are defined as a temporary overflow of water onto lands that are not normally covered by water. Flooding results from the overflow of major rivers and tributaries, storm surges, and/or inadequate local drainage. Floods can cause loss of life, property damage, crop/livestock damage, and water supply contamination. Floods can also disrupt travel routes on roads and bridges. Inland floods are most likely to occur in the spring due to the increase in rainfall and melting of snow; however, floods can occur at any time of the year. A sudden thaw in the winter or a major downpour in the summer can cause flooding because there is suddenly a lot of water in one place with nowhere to go. 100-year Floodplain Events • Floodplains are usually located in lowlands near rivers, and flood on a regular basis. The term 100-year

flood does not mean that a flood will occur once every 100 years. Rather, it is a statement of probability that scientists and engineers use to describe how one flood compares to others that are likely to occur. It is more accurate to use the phrase “1% annual chance of flood.” What this means is that there is a 1% chance of a flood of that size happening in a year.

Rapid Snow Pack Melt • Warm temperatures and heavy rains cause rapid snowmelt. Quickly melting snow coupled with

moderate to heavy rains are prime conditions for flooding. River Ice Jams • Rising waters in early spring breaks ice into chunks, which float downstream and often pile up, causing

flooding. Small rivers and streams pose special flooding risks because they are easily blocked by jams. Ice collecting in river bends and against structures presents significant flooding threats to bridges, roads, and the surrounding lands.

Severe Storms • Flooding associated with severe storms can inflict heavy damage to property. Heavy rains during severe

storms are a common cause of inland flooding. Beaver Dams and Lodging • Flooding associated with beaver dams and lodging can cause road flooding or flooding damage to

property.

Drought A drought is defined as a long period of abnormally low precipitation, especially one that adversely affects growing or living conditions. Droughts are rare in New Hampshire. They generally are not as damaging and disruptive as floods and are more difficult to define. The effect of droughts is indicated through measurements of soil moisture, groundwater levels, and stream-flow. However, not all of these indicators will be minimal during a drought. For example, frequent minor rainstorms can replenish the soil moisture without raising ground-water levels or increasing stream-flow. Low stream-flow correlates with low ground-water levels because ground-water discharge to streams and rivers maintains stream-flow during extended dry periods. Low stream-flow and low ground-water levels commonly cause diminished water supply. Extreme Heat Extreme heat is characterized by abnormally high temperatures and/or longer than average time periods of high temperatures. These event conditions may impact the health of both humans and livestock. The State Hazard Mitigation Team is conducting additional research to more accurately characterize extreme heat hazards. Wildfire Wildfire is defined as an uncontrolled and rapidly spreading fire.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (59)

Forest Fires and Grass Fires • A forest fire is an uncontrolled fire in a woody area. They often occur during drought and when woody

debris on the forest floor is readily available to fuel the fire. Grass fires are uncontrolled fires in grassy areas.

Earthquake New England is considered a moderate risk earthquake zone. An earthquake is a rapid shaking of the earth caused by the breaking and shifting of rock beneath the earth’s surface. Earthquakes can cause buildings and bridges to collapse, disrupt gas, electric, water and phone lines, and often cause landslides, flash floods, fires, and avalanches. Larger earthquakes usually begin with slight tremors but rapidly take the form of one or more violent shocks, and end in vibrations of gradually diminishing force called aftershocks. The underground point of origin of an earthquake is called its focus; the point on the surface directly above the focus is the epicenter. The magnitude and intensity of an earthquake is determined by the use of scales such as the Richter scale and Mercalli scale. Subsidence The collapse of the Earth’s surface elevation due to the removal of subsurface support. Events range from broad regional lowering of the land surface that occurs over long periods of time, to sudden localized collapse. Radon Radon is a naturally occurring radioactive gas with carcinogenic properties. The gas is a common problem in many states, including New Hampshire. Data collected by the NH Office of Community and Public Health’s Bureau of Radiological Health indicates that one third of the houses in New Hampshire have indoor radon levels that exceed the U.S. Environmental Protection Agency’s “action level” of four Pico curies per liter for at least some portion of the year. Radon may also enter homes dissolved in drinking water from drilled wells. A higher level of radon in water from individual drilled wells is a common occurrence in New Hampshire. Tornado A tornado is a violent windstorm characterized by a twisting, funnel shaped cloud. They develop when cool air overrides a layer of warm air, causing the warm air to rise rapidly. The atmospheric conditions required for the formation of a tornado include great thermal instability, high humidity, and the convergence of warm, moist air at low levels with cooler, drier air aloft. Most tornadoes remain suspended in the atmosphere, but if they touch down they become a force of destruction. Tornadoes produce the most violent winds on earth, at speeds of 280 mph or more. In addition, tornadoes can travel at a forward speed of up to 70 mph. Damage paths can be in excess of one mile wide and 50 miles long. Violent winds and debris slamming into buildings cause the most structural damage. The Fujita Scale is the standard scale for rating the severity of a tornado as measured by the damage it causes. A tornado is usually accompanied by thunder, Lightning, heavy rain, and a loud “freight train” noise. In comparison to a hurricane, a tornado covers a much smaller area but can be more violent and destructive. Hurricane A hurricane is a tropical cyclone in which winds reach speeds of 74 miles per hour or more and blow in a large spiral around a relatively calm center. The eye of the storm is usually 20-30 miles wide and may extend over 400 miles. High winds and flooding are primary causes of hurricane-inflicted loss of life and property damage.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (60)

Severe Wind Significantly high winds occur especially during tornadoes, hurricanes, winter storms and thunderstorms. Falling objects and downed power lines are dangerous risks associated with high winds. In addition, property damage and downed trees are common during severe wind occurrences. Downburst • A downburst is a severe, localized wind blasting down from a thunderstorm. These “straight line” winds

are distinguishable from tornadic activity by the pattern of destruction and debris. Downbursts fall into two categories:

• Microburst, which covers an area less than 2.5 miles in diameter, and • Macroburst, which covers an area at least 2.5 miles in diameter.

Lightning Lightning is a giant spark of electricity that occurs within the atmosphere or between the atmosphere and the ground. As lightning passes through the air, it heats the air to a temperature of about 50,000 degrees Fahrenheit, considerably hotter than the surface of the sun. Fires are a likely result of lightning strikes, and lightning strikes can cause death, injury, and property damage. Extreme Winter Weather Ice and snow events typically occur during the winter months and can cause loss of life, property damage and tree damage. Heavy Snow Storms • A winter storm can range from moderate snow to blizzard conditions. Blizzard conditions are

considered blinding, wind-driven snow over 35 mph that lasts several days. A severe winter storm deposits four or more inches of snow during a 12-hour period or six inches of show during a 24-hour period.

Ice Storms • An ice storm involves rain, which freezes on impact. Ice coating at least one-fourth inch of thickness is

heavy enough to damage trees, overhead wires and similar objects. Ice storms often produce widespread power outages.

Nor’easter • A Nor’easter is a large weather system traveling from South to North passing along or near the seacoast.

As the storm approaches New England and its intensity becomes increasingly apparent, the resulting counterclockwise cyclonic winds impact the coast and inland areas from a Northeasterly direction. The sustained winds may meet or exceed hurricane force, with larger bursts, and may exceed hurricane events by many hours (or days) in terms of duration.

Snow Avalanches A snow avalanche is a slope failure consisting of a mass of rapidly moving, fluidized snow that slides down a mountainside. The flow can be composed of ice, water, soil, rock and trees. Man-Made Hazards Hazardous Materials • Hazardous materials spills or releases can cause damage of loss to life and property. Short or long-term

evacuation of local residents and businesses may be required, depending on the nature and extent of the incident.

Dam Breach and Failure • Dam failure results in rapid loss of water that is normally held by the dam. These kinds of floods are

extremely dangerous and pose a significant threat to both life and property.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (61)

APPENDIX B: RESOURCES

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (62)

RESOURCES USED IN THE PREPARATION OF THIS PLAN

NH BEM’s State of New Hampshire Natural Hazards Mitigation Plan (9/99)

Massachusetts’s Flood Hazard Mitigation Planning: A Community Guide (6/97)

SWRPC’s Hazard Mitigation Planning for New Hampshire Communities (10/02)

BEM’s Hazard Mitigation Plan for New Hampshire Communities (12/97 draft document)

BEM / NH OEP’s Flood Insurance Handbook (4/94)

FEMA’s Community Based Hazard Mitigation Planning: Lowering the Risks and Costs of Disasters (8/98)

FEMA’s Understanding Your Risks: Identifying Hazards and Estimating Losses, August 2001

The Local Mitigation Strategy: A Guidebook for Florida Cities and Counties (4/98)

Texas Community Official’s Primer on Floodplain Planning Strategies and Tools (6/94)

City of Keene, NH’s Flood Hazard Mitigation Plan (2/2000 final draft)

City of Saco, ME’s All Hazard Mitigation Plan (1/2000)

City of Montpelier, VT’s Flood Hazard Mitigation Plan (5/98 draft)

Town of Rindge, NH’s Master Plan (2001 update)

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (63)

Agencies

New Hampshire Bureau of Emergency Management (BEM) ...............................................................271-2231 Hazard Mitigation Section ......................................................................................................................271-2231

Federal Emergency Management Agency (FEMA) ..................................................................... (877) 336-2734 NH Regional Planning Commissions:

Central NH Regional Planning Commission ..........................................................................................226-6020 Lakes Region Planning Commission ......................................................................................................279-8171 Nashua Regional Planning Commission .................................................................................................883-0366 North Country Council ...........................................................................................................................444-6303 Rockingham Planning Commission ........................................................................................................778-0885 Southern New Hampshire Planning Commission ...................................................................................669-4664 Southwest Region Planning Commission ...............................................................................................357-0557 Strafford Regional Planning Commission ..............................................................................................742-2523 Upper Valley Lake Sunapee Regional Planning Commission ................................................................448-1680

NH Executive Department:

Governor’s Office of Energy and Community Services .........................................................................271-2611 New Hampshire Office of Energy and Planning ....................................................................................271-2155

NH Department of Cultural Resources: .................................................................................................271-2540

Division of Historical Resources ............................................................................................................271-3483 NH Department of Environmental Services: .........................................................................................271-3503

Air Resources .........................................................................................................................................271-1370 Air Toxins Control Program....................................................................................................................271-0901 Asbestos Program....................................................................................................................................271-1373 Childhood Lead Poisoning Prevention Program......................................................................................271-5733 Environmental Health Tracking Program................................................................................................271-4072 Environmental Toxicology Program .......................................................................................................271-3994 Health Risk Assessment Program............................................................................................................271-6909 Indoor Air Quality Program.....................................................................................................................271-3911 Occupational Health and Safety Program................................................................................................271-2024 Radon Program........................................................................................................................................271-4764 Geology Unit ...........................................................................................................................................271-3503 Pollution Preventive Program..................................................................................................................271-6460 Waste Management ................................................................................................................................271-2900 Water Supply and Pollution Control .......................................................................................................271-3414 Rivers Management and Protection Program .........................................................................................271-8801

NH Office of Energy & Planning (OEP) .................................................................................................271-2155 NH Municipal Association .......................................................................................................................224-7447 NH Fish and Game Department .............................................................................................................271-3421 Region 1, Lancaster................................................................................................................................788-3164 Region 2, New Hampton ........................................................................................................................744-5470 Region 3, Durham ..................................................................................................................................868-1095 Region 4, Keene .....................................................................................................................................352-9669 NH Department of Resources and Economic Development: ................................................................271-2411 Economic Development ..................................................................................................................... 271-2629 Travel and Tourism................................................................................271-6870

Division of Forests and Lands ................................................................................................................271-2214

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (64)

Division of Parks and Recreation ...........................................................................................................271-3556 Design, Development, and Maintenance .................................................................................................271-2411

NH Department of Transportation .........................................................................................................271-3734 Northeast States Emergency Consortium, Inc. (NESEC) ............................................................ (781) 224-9876

US Department of Commerce: ....................................................................................................... (202) 482-2000

National Oceanic and Atmospheric Administration: National Weather Service; Taunton, Massachusetts ..................................................................... (508) 824-5116

US Department of the Interior: ........................................................................................................ 202-208-3100

US Fish and Wildlife Service .................................................................................................................225-1411 US Geological Survey ............................................................................................................................225-4681 US Army Corps of Engineers ........................................................................................................ (978) 318-8087

US Department of Agriculture:

Natural Resource Conservation Service .................................................................................................868-7581 Cheshire County, Walpole....................................................................................................................756-2988 Sullivan County, Newport ....................................................................................................................863-4297 Hillsborough County, Milford ................................................................................................. 673-2409 Ext. #4

Mitigation Funding Resources

404 Hazard Mitigation Grant Program (HMGP).........................................NH Bureau of Emergency Management 406 Public Assistance and Hazard Mitigation.............................................NH Bureau of Emergency Management Community Development Block Grant (CDBG) .......................................... NH BEM, NH OSP, also refer to RPC Dam Safety Program ............................................................................. NH Department of Environmental Services Disaster Preparedness Improvement Grant (DPIG) ....................................NH Bureau of Emergency Management Emergency Generators Program by NESEC‡ .............................................NH Bureau of Emergency Management Emergency Watershed Protection (EWP) Program.......................USDA, Natural Resources Conservation Service Flood Mitigation Assistance Program (FMAP) ......................................................................... NH BEM, NH OEP Flood Plain Management Services (FPMS) ................................................................US Army Corps of Engineers Mitigation Assistance Planning (MAP).......................................................NH Bureau of Emergency Management Mutual Aid for Public Works.......................................................................................... NH Municipal Association National Flood Insurance Program (NFIP) † .............................................................................. NH OSP, NH BEM Power of Prevention Grant by NESEC‡ ......................................................NH Bureau of Emergency Management Project Impact .............................................................................................NH Bureau of Emergency Management Roadway Repair & Maintenance Program(s).......................................................NH Department of Transportation Section 14 Emergency Stream Bank Erosion & Shoreline Protection …………….…US Army Corps of Engineers Section 103 Beach Erosion………………………………………………………...…US Army Corps of Engineers Section 205 Flood Damage Reduction…………………………………………….....US Army Corps of Engineers Section 208 Snagging and Clearing .............................................. US Army Corps of Engineers Shoreline Protection Program………………………………………….NH Department of Environmental Services Various Forest and Lands Program(s)...........................NH Department of Resources and Economic Development Wetlands Programs ............................................................................... NH Department of Environmental Services

‡NESEC – Northeast States Emergency Consortium, Inc. is a 501(c)(3), not-for-profit natural disaster, multi-hazard mitigation and emergency management organization located in Wakefield, Massachusetts. Please, contact NH BEM for more information. † Note regarding National Flood Insurance Program (NFIP) and Community Rating System (CRS): The National Flood Insurance Program has developed suggested floodplain management activities for those communities who wish to more thoroughly manage or reduce the impact of flooding in their jurisdiction. Through use of a rating system (CRS rating), a community’s floodplain management efforts can be evaluated for effectiveness. The rating, which indicates an above average floodplain management effort, is then factored into the premium cost for flood insurance policies sold in the community. The higher the rating achieved in that community, the greater the reduction in flood insurance premium costs for local property owners. The NH Office of Energy & Planning can provide additional information regarding participation in the NFIP-CRS Program.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (65)

Websites Sponsor Internet Address Summary of Contents

Natural Hazards Research Center, U. of Colorado

http://www.colorado.edu/hazards/ Searchable database of references and links to many disaster-related websites.

Atlantic Hurricane Tracking Data by Year

http://wxp.eas.purdue.edu/hurricane Hurricane track maps for each year, 1886 – 1996

National Emergency Management Association

http://nemaweb.org Association of state emergency management directors; list of mitigation projects.

NASA – Goddard Space Flight Center “Disaster Finder:

http://www.gsfc.nasa.gov/ndrd/disaster/

Searchable database of sites that encompass a wide range of natural disasters.

NASA Natural Disaster Reference Database

http://ltpwww.gsfc.nasa.gov/ndrd/main/html

Searchable database of worldwide natural disasters.

U.S. State & Local Gateway http://www.statelocal.gov/ General information through the federal-state partnership.

National Weather Service http://nws.noaa.gov/ Central page for National Weather Warnings, updated every 60 seconds.

USGS Real Time Hydrologic Data http://h20.usgs.gov/public/realtime.html

Provisional hydrological data

Dartmouth Flood Observatory http://www.dartmouth.edu/artsci/geog/floods/

Observations of flooding situations.

FEMA, National Flood Insurance Program, Community Status Book

http://www.fema.gov/fema/csb.htm Searchable site for access of Community Status Books

Florida State University Atlantic Hurricane Site

http://www.met.fsu.edu/explores/tropical.html

Tracking and NWS warnings for Atlantic Hurricanes and other links

National Lightning Safety Institute http://lightningsafety.com/ Information and listing of appropriate publications regarding lightning safety.

NASA Optical Transient Detector http://www.ghcc.msfc.nasa.gov/otd.html

Space-based sensor of lightning strikes

LLNL Geologic & Atmospheric Hazards

http://wwwep.es.llnl.gov/wwwep/ghp.html

General hazard information developed for the Dept. of Energy.

The Tornado Project Online http://www.tornadoroject.com/ Information on tornadoes, including details of recent impacts.

National Severe Storms Laboratory http://www.nssl.uoknor.edu/ Information about and tracking of severe storms.

Independent Insurance Agents of America IIAA Natural Disaster Risk Map

http://www.iiaa.iix.com/ndcmap.htm A multi-disaster risk map.

Earth Satellite Corporation http://www.earthsat.com/ Flood risk maps searchable by state. USDA Forest Service Web http://www.fs.fed.us/land Information on forest fires and land

management.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (66)

APPENDIX C: HAZARD MITIGATION RESOURCE PROFILES

The following are fact sheets about the various hazard mitigation grant programs

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (67)

♦ HAZARD MITIGATION GRANT PROGRAM (cont…)

What types of projects can be funded by the HMGP?

HMGP funds may be used to fund projects that will reduce or eliminate the losses from future disasters. Projects must provide a long-term solution to a problem, for example, elevation of a home to reduce the risk of flood damages as opposed to buying sandbags and pumps to fight the flood. In addition, a project's potential savings must be more than the cost of implementing the project. Funds may be used to protect either public or private property or to purchase property that has been subjected to, or is in danger of, repetitive damage. Examples of projects include, but are not limited to:

• Acquisition of real property for willing sellers and demolition or relocation of buildings to convert the property to open space use

• Retrofitting structures and facilities to minimize damages from high winds, earthquake, flood, wildfire, or other natural hazards

• Elevation of flood prone structures • Development and initial implementation of vegetative management programs • Minor flood control projects that do not duplicate the flood prevention activities of other Federal agencies • Localized flood control projects, such as certain ring levees and floodwall systems, that are designed

specifically to protect critical facilities • Post-disaster building code related activities that support building code officials during the reconstruction

process

What are the minimum project criteria?

There are five issues you must consider when determining the eligibility of a proposed project.

• Does your project conform to your State's Hazard Mitigation Plan? • Does your project provide a beneficial impact on the disaster area, i.e. the State? • Does your application meet the environmental requirements? • Does your project solve a problem independently? • Is your project cost-effective?

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (68)

Community Development Block Grant

• U.S. Dept. of Housing and Urban Development • Funds for a Declared Disaster’s "Unmet

Needs" • Projects must meet one of three National

Objectives • Provide a direct benefit to low and moderate

income persons or households • Prevent or eliminate slums and blight • Eliminate conditions which seriously and

immediately threaten the public health and welfare

Additional conditions with respect to the expenditure of these funds includes the provision that at least 50% of the grant award must be expended in a manner which benefits individuals who earn 80% or less than the area’s (county’s) median income.

♦ COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM Title 1 of the Housing and Community Development Act of 1974 authorized the Community Development Block Grant (CDBG) program. The primary purpose of the CDBG program is the development of viable communities by providing decent housing, suitable living environments, and expanding economic opportunities, principally for low and moderate income people. The program is sponsored by the US Department of Housing and Urban Development (HUD) and the New Hampshire program is administered through the Community Development Finance Authority (CDFA).

Typically, each year the New Hampshire CDBG program receives approximately $10 million from HUD to use towards the CDBG Programs: Housing, Public Facilities, Economic Development, Feasibility Studies, and Emergencies and Unanticipated Events. Since 1983, over 773 grants and over $188 million have been funded throughout New Hampshire.

Any municipality or county, other than entitlement communities of Rochester, Dover, Portsmouth, Manchester, and Nashua, is eligible to apply to CDFA for CDBG funding. A nonprofit agency may also apply through its municipality or county as a sub-recipient of CDBG money. All eligible municipalities and counties can apply for up to $500,000 in CDBG funds per year. Entitlement communities are those communities that, due to their population, receive CDBG money directly from HUD as a special set-aside. These Federal funds are provided through the U.S. Department of Housing and Urban Development (HUD) and are administered by the CDBG Program of the New Hampshire Office of State Planning. The specific CDBG funds designated for hazard mitigation purposes are made available to address "unmet needs" pursuant to a given Disaster Declaration to States which request them. For these funds, project selection guidance is provided by NHOEM and NHOSP administers the grant.

Mitigation Programs of Other NH State Agencies The following agencies of the State of New Hampshire are directly or indirectly involved in activities that

include Hazard Mitigation Planning and/or program implementation: NH Department of Transportation Bureau of Repair and Maintenance

NH OEP/NFIP Program NH OEP Coastal Program

NH DRED Division of Forests and Lands NH DES Water Resources Division – Dam Safety Program

NH DES Wetlands Program NH DES Shoreland Protection Program

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (69)

APPENDIX D: MATRIX OF FEDERAL ALL-

HAZARDS GRANTS

This matrix provides information about key all-hazards grant programs from the

Departments of Homeland Security, Justice, Transportation, Health and Human Services, and Education under which state, local, and tribal governments, first responders, and the

public are eligible to receive preparedness, response, recovery, mitigation, and prevention assistance.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (70)

FEDERAL PREPAREDNESS GRANT PROGRAMS AS REPORTED TO DHS/FEMA NIMS INTEGRATION CENTER

Organization Grant Programs Identified Environmental Protection Agency (EPA)

1. Security Enhancement and Emergency Preparedness Planning at Water Utilities 2. EPA Grant and Contract Vehicles to move funding from DHS to localities for the regular retrieval of Bio Watch sampling filters and delivery for analysis

Nuclear Regulatory Commission (NRC)

1. NRC provides pharmaceutical intervention to states with populations within the 10-mile emergency planning zone of Commercial nuclear power plants.

Department of Justice (DOJ)

1. State Domestic Preparedness Equipment Support Program 2. Antiterrorism and Emergency Assistance Program 3. Domestic Antiterrorism Technology Development Program 4. COPS Interoperable Communications Technology Program

Department of Agriculture (USDA)

1. State Fire Assistance 2. Volunteer Fire Assistance 3. First Responder Initiative

Department of Energy (DOE)

1. Working Agreement: DOE, the Shoshone-Bannock Tribes and the Idaho National Engineering and Environmental Laboratory 2. Environmental oversight and Monitoring Agreement: Office of Nuclear Energy and the State of Idaho 3. Agreement-in-Principle: Waste Isolation Pilot Plant (DOE), the Western Governors Association and the State of Idaho 4. Office of Civilian Radioactive Waste Management Training Program 5. Agreement-in-Principle with the State of Texas Energy Conservation Office 6. Agreement-in-Principle with the six counties and the State of Nevada 7. S.C. Emergency Management Division Agreement-in-Principle Grants 8. S.C. Dept. of Health and Environmental Control Agreement-in-Principle Grants 9. Georgia Emergency Management Division Agreement-in-Principle Grants 10. Cooperative Agreement: Western Governors Association, Southern States Energy Board, mid-West and North East Council of State Governors 11. Office of River Protection Grant 12. Memorandum of Understanding (MOU): DOE and City of Miamisburg 13. Ohio Field Office MOU with West Valley, N.Y., Volunteer Hose Company

Tennessee Valley Authority (TVA)

1. Supplemental Agreements: Tennessee Emergency Management Agency and Alabama Emergency Management Agency, for off-site support of nuclear power plant radiological emergency plans

Environmental Protection Agency (EPA)

1. Security Enhancement and Emergency Preparedness Planning at Water Utilities 2. EPA Grant and Contract Vehicles to move funding from DHS to localities for the regular retrieval of Bio Watch sampling filters and delivery for analysis

Nuclear Regulatory Commission (NRC)

1. NRC provides pharmaceutical intervention to states with populations within the 10-mile emergency planning zone of Commercial nuclear power plants.

Department of Justice (DOJ)

1. State Domestic Preparedness Equipment Support Program 2. Antiterrorism and Emergency Assistance Program 3. Domestic Antiterrorism Technology Development Program 4. COPS Interoperable Communications Technology Program

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (71)

FEDERAL PREPAREDNESS GRANT PROGRAMS AS REPORTED TO DHS/FEMA NIMS INTEGRATION CENTER

Organization Grant Programs Identified Department of Agriculture (USDA)

1. State Fire Assistance 2. Volunteer Fire Assistance 3. First Responder Initiative

Department of Energy (DOE)

1. Working Agreement: DOE, the Shoshone-Bannock Tribes and the Idaho National Engineering and Environmental Laboratory 2. Environmental oversight and Monitoring Agreement: Office of Nuclear Energy and the State of Idaho 3. Agreement-in-Principle: Waste Isolation Pilot Plant (DOE), the Western Governors Association and the State of Idaho 4. Office of Civilian Radioactive Waste Management Training Program 5. Agreement-in-Principle with the State of Texas Energy Conservation Office 6. Agreement-in-Principle with the six counties and the State of Nevada 7. S.C. Emergency Management Division Agreement-in-Principle Grants 8. S.C. Dept. of Health and Environmental Control Agreement-in-Principle Grants 9. Georgia Emergency Management Division Agreement-in-Principle Grants 10. Cooperative Agreement: Western Governors Association, Southern States Energy Board, mid-West and North East Council of State Governors 11. Office of River Protection Grant 12. Memorandum of Understanding (MOU): DOE and City of Miamisburg 13. Ohio Field Office MOU with West Valley, N.Y., Volunteer Hose Company

Tennessee Valley Authority (TVA)

1. Supplemental Agreements: Tennessee Emergency Management Agency and Alabama Emergency Management Agency, for off-site support of nuclear power plant radiological emergency plans

Department of Education 1. School Emergency Response and Crisis Management Plan Discretionary Grant Program

Department of Homeland Security (DHS)

1. State Homeland Security Grant Program 2. Assistance to Firefighters Grant Program 3. Interoperable Communications Equipment Grant 4. SARA Title III Training Program 5. Urban Search and Rescue 6. State and Local Emergency Operation Centers 7. Community Emergency Response Teams 8. Emergency Management Performance Grants 8. Chemical Stockpile Emergency preparedness Program 10. State and Local Emergency operations Planning Grants 11. Citizen Corps 12. Metropolitan Medical Response System 13. National Fire Academy Training Grants 14. First Responder Grants

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (72)

FEDERAL PREPAREDNESS GRANT PROGRAMS AS REPORTED TO DHS/FEMA NIMS INTEGRATION CENTER

Organization Grant Programs Identified Department of Health and Human Services (HHS)

1. Public Health and Social Services Emergency Fund 2. State Rural Hospital Flexibility Program 3. EMS for Children 4. Superfund Hazardous Substances Basic Research and Education 5. Metropolitan Medical Response System 6. Immunization Research, Demonstration, Public Information and Education 7. Surveillance of Hazardous Substance Emergency Events 8. Human Health Studies, Applied Research and Development 9. Immunization Grants 10. Bioterrorism Preparedness Programs

Department of the Interior (DOI)

1. Rural Fire Assistance Program 2. Earthquake Hazards Reduction Program 3. Volcano Hazards Reduction Program

Department of Transportation (DOT)

1. Hazardous Materials Emergency Preparedness Training and Planning Grants 2. Airport Improvement Program 3. Satellite-based Mobile Communications Tracking System for Hazardous Materials 4. Un-tethered Trailer Tracking and Security Project 5. Operation Respond 6. Port Security Grant Program 7. Maritime Transportation Security Act Training 8. Ready Reserve Force 9. Priority Use and Allocation of Shipping Service, Containers and Chassis; Port Facilities, Services for National Security and National Defense Related Operations

AUGUST 2005

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (73)

APPENDIX E DOCUMENTATION OF THE

PLANNING PROCESS

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (74)

Rindge Hazard Mitigation Team

Meeting #1

AGENDA

April 20, 2006

7:00 p.m.

Rindge Town Offices

1) Introduction 2) Purpose of Committee

• Why selected to serve on Committee • What we are doing and why

3) What is Hazard Mitigation Planning?

• PowerPoint Presentation on Hazard Mitigation

4) Step 1: Organize Hazard Mitigation Team

• Establish a chairperson/point of contact 5) What must we do to prepare a Hazard Mitigation Plan?

• Explain/set milestones (approximate number of committee meetings) • Agree on next committee meeting date

6) Question and Answer Period 7) Set Goals for Next Meeting

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (75)

Rindge Hazard Mitigation Team

Meeting #2

AGENDA

May 22, 2006

7:00 p.m.

Rindge Town Offices

1) Step 2: Identify Hazards (past and potential) on Base Map

• What are the hazards? • What is at risk from those hazards?

2) Develop Base Map with Critical Facilities

• Identify Critical Facilities on Base Map. Please refer to enclosed packet for

descriptions of facilities to be included.

3) Question and Answer Period

4) Set Goals for Next Meeting

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (76)

Rindge Hazard Mitigation Team

Meeting #3

AGENDA

June 6, 2006

10:00 a.m.

Rindge Town Offices

1) Review and finish Step 2: Identifying Hazards

• Past and Potential • Critical Facilities

2) Step 3: Assessing Vulnerability

• Estimating Potential Losses 3) Step 4: Analyzing Development Trends

• Looking at Community Change • Review Development Regulations for Development Management • Map Out Development Patterns

4) Step 5: Existing Mitigation Strategies

• Identifying What’s in Place • What are we Already Doing? • Identify gaps in Current Protection

5) Question and Answer Period 6) Set Goals for Next Meeting

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (77)

Rindge Hazard Mitigation Team

Meeting #4

AGENDA

July 11, 2006

10:00 a.m.

Rindge Town Offices

1) Review Step 5: Identifying Plans in Place

• Where are the gaps? • What are we already doing?

2) Step 6, Part 1: Brainstorming Mitigation Actions

• What actions can be taken? • Evaluating Action Feasibility

3) Step 6, Part 2: Potential Hazards Action Matrix

• Identify objectives and actions for mitigating potential hazards identified in Step 2 Evaluate Actions -“What is Feasible?” • Fill out the Evaluation Chart for each action.

Grade/Rank the actions according to the Evaluation Chart

• Match the action against the STAPLEE criteria Grade/Rank the actions according to the STAPLEE criteria

4) Step 7: Select Actions (Establishing Priorities)

Further refine the list of mitigation objectives developed in Steps 5 & 6 that are appropriate to your community and prioritize them in order of importance.

• Establish a minimum acceptable level for actions. • Select actions which best suit community’s needs. • Prioritize actions • Include actions that can be implemented quickly

5) Question and Answer Period 6) Set Goals for Next Meeting

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (78)

Rindge Hazard Mitigation Team

Meeting #5

AGENDA

August 8, 2006

10:00 a.m.

Rindge Town Offices

1) Review Step 6: Potential Mitigation Actions

• What actions could be taking? • Evaluating Potential Actions?

2) Step 7: Select Actions (Establishing Priorities)

Further refine the list of mitigation objectives developed in Steps 5 & 6 that are appropriate to your community and prioritize them in order of importance.

• Establish a minimum acceptable level for actions. • Select actions which best suit community’s needs. • Prioritize actions • Include actions that can be implemented quickly

3) Step 8: Develop a Strategy (How do we Implement Actions?)

The Committee will develop a strategy that outlines: • Who is responsible for implementing each prioritized action. • When these actions will be implemented. • How the community will fund the projects.

4) Question and Answer Period 5) Set Goals for Next Meeting

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (79)

Rindge Hazard Mitigation Team

Meeting #6

AGENDA

September 19, 2006

10:00 a.m.

Rindge Town Offices

1. Review and Complete

• Step 7 - Establishing Priorities. • Step 8 - Implementation Strategies

2. Review and Revise as necessary previous steps

Review prior steps and collect any information which might have been overlooked. We will review the information collected and the maps created.

3. Discuss next steps

Next steps will include review of draft plan by Committee, review by FEMA, and adoption of plan by Board of Selectmen.

4. Question and Answer Period

5. Adjourn

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (80)

Rindge Hazard Mitigation Team

Meeting #7

AGENDA

November 2, 2006

1) Review & Revise as necessary final draft of the Rindge Hazard Mitigation Plan 2) Discuss next steps for the Rindge Hazard Mitigation Plan including FEMA review

and adoption by the Board of Selectmen.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (81)

APPENDIX F PUBLIC RELATIONS

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (82)

TOWN OF RINDGE Office of the Selectmen

PUBLIC NOTICE

The Hazard Mitigation Committee

will be holding a public meeting at the Rindge Town Office on

Thursday, April 20

7:00 p.m.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (83)

TOWN OF RINDGE Office of the Selectmen

PUBLIC NOTICE

The Hazard Mitigation Committee

will be holding a public meeting at the Rindge Town Office on

Monday, May 22

7:00 p.m.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (84)

TOWN OF RINDGE Office of the Selectmen

PUBLIC NOTICE

The Hazard Mitigation Committee

will be holding a public meeting at the Rindge Town Office on

Tuesday, July 11

10:00 a.m.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (85)

APPENDIX G PROJECT STATUS SHEETS

The following form can be used to keep track of projects identified in the hazard mitigation plan that are in progress or that have been completed.

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (86)

HAZARD MITIGATION PLAN- PROJECT STATUS

Project Title/Description Page #

in Plan Date of Project

Completion Comments

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH· 2014. 1. 24.· HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (87)

HAZARD MITIGATION PLAN- PROJECT STATUS

Project Title/Description Page # in Plan

Date of Project Completion

Comments

HAZARD MITIGATION PLAN TOWN OF RINDGE, NH · 2014. 1. 24. · HAZARD MITIGATION PLAN TOWN OF RINDGE, NH Courtesy of the Rindge Historical Society Prepared by the: Town of Rindge Hazard - [PDF Document] (2024)

FAQs

What are examples of hazard mitigation projects? ›

Public Assistance Hazard Mitigation Project Examples
  • Constructing floodwalls around damaged facilities.
  • Installing new drainage facilities (including culverts) along a damaged road.
  • Adding fire-suppression systems at facilities damaged by wildfire.
Dec 12, 2023

What is hazard mitigation? ›

Hazard Mitigation is defined as any sustained action taken to reduce or eliminate the long-term risk to life and property from hazard events. It is an on-going process that occurs before, during, and after disasters and serves to break the cycle of damage and repair in hazardous areas.

What are the 4 types of hazard mitigation? ›

The suggested mitigation actions are summarized into four types: (1) Local Planning and Regulations, (2) Structure and Infrastructure Projects, (3) Natural Systems Protection, and (4) Education and Awareness Programs.

What are the 3 parts of a hazard mitigation plan? ›

Hazard mitigation plans can address a range of natural and human-caused hazards. They typically include four key elements: 1) a risk assessment, 2) capability assessment, 3) mitigation strategy, and 4) plan maintenance procedures.

What are the 4 commonly used risk mitigation process? ›

What are the four risk mitigation strategies? There are four common risk mitigation strategies: avoidance, reduction, transference, and acceptance.

What is an example of mitigating risk in a project? ›

For example, to mitigate risk of new product production, a project team may decide to implement product testing to avoid the risk of product failure before the final production is approved.

What is a real life example of risk mitigation? ›

But you can mitigate safety and business risks by reducing their likelihood of occurring and/or the impact they could have. For example, an industrial bakery can't avoid having massive heat sources active, but it can take steps to reduce the danger to employees and property.

Top Articles
Latest Posts
Recommended Articles
Article information

Author: Rev. Porsche Oberbrunner

Last Updated:

Views: 5662

Rating: 4.2 / 5 (73 voted)

Reviews: 80% of readers found this page helpful

Author information

Name: Rev. Porsche Oberbrunner

Birthday: 1994-06-25

Address: Suite 153 582 Lubowitz Walks, Port Alfredoborough, IN 72879-2838

Phone: +128413562823324

Job: IT Strategist

Hobby: Video gaming, Basketball, Web surfing, Book restoration, Jogging, Shooting, Fishing

Introduction: My name is Rev. Porsche Oberbrunner, I am a zany, graceful, talented, witty, determined, shiny, enchanting person who loves writing and wants to share my knowledge and understanding with you.